Contract
No: HK/2011/07 Wanchai Development Phase
II and Sampling, Field Measurement and
Testing Works
(Stage 2) Environmental Permit no. EP-356/2009, Further Evironmental permit nos.
fep-01/356/2009, fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009 and Fep-05/356/2009 Monthly Environmental Monitoring & Audit Report
- September 2012 -
|
CLIENTS: |
|
Civil Engineering and Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point Wanchai, H.K. Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond
Dai Environmental
Team Leader |
|
DATE: |
|
11 October 2012 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
3. Status of Regulatory Compliance
3.1 Status of Environmental Licensing and Permitting under
the Project
5.2 Real-time Noise Monitoring
6.2 Real-time noise Monitoring
6.5 Review of the Reasons for and the Implications of
Non-compliance
6.6 Summary of action taken in the event of and follow-up
on non-compliance
7. Cumulative Construction Impact due to the Concurrent
Projects
9. Complaints,
Notification of Summons and Prosecution
lIST OF TABLES
Table I Summary
of Water Quality Monitoring Exceedances in Reporting Month
Table II Summary
of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month
Table 2.1 Schedule 2
Designated Projects under this Project
Table 2.2 Details
of Individual Contracts under the Project
Table 2.3 Contact
Details of Key Personnel
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/11
Table 3.3 Summary
of submission status under FEP-01/356/2009 Condition
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Table 3.5 Summary
of submission status under FEP-02/356/2009 Condition
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Table 3.7 Summary
of submission status under FEP-03/356/2009 Condition
Table 3.8 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/15
Table 3.9 Summary
of submission status under FEP-04/356/2009 Condition
Table 3.10 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2010/06
Table 3.11 Summary of
submission status under EP-356/2009 and FEP-05/356/2009 Condition
Table 3.12 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/19
Table 4.1 Noise
Monitoring Station
Table 4.2 Real
Time Noise Monitoring Station
Table 4.3 Air
Monitoring Station
Table 4.4 Marine
Water Quality Stations for Water Quality Monitoring
Table 4.5 Marine
Water Quality Monitoring Frequency and Parameters
Table 4.6 Marine
Water Quality Stations for Enhanced Water Quality Monitoring
Table 4.7 Marine
Water Quality Stations for Additional DO Monitoring
Table 5.1 Noise
Monitoring Stations for Contract no. HY/2009/11
Table 5.2 Noise
Monitoring Station for Contract nos. HK/2009/01, HK/2009/02 and HK/2010/06
Table 5.3 Noise
Monitoring Station for Contract no. HY/2009/15
Table 5.4 Noise
Monitoring Station for Contract no. HY/2009/19
Table 5.5 Real
Time Noise Monitoring Station for Contract no. HY/2009/11 and HY/2009/19
Table 5.6 Air
Monitoring Stations for Contract no. HY/2009/11
Table 5.7 Air
Monitoring Stations for Contract no. HK/2009/01
Table 5.8 Air
Monitoring Station for Contract no. HK/2009/02
Table 5.9 Air
Monitoring Station for Contract no. HY/2009/15
Table 5.10 Air
Monitoring Stations for Contract no. HY/2009/19
Table 5.11 Water
Monitoring Stations for Contract no. HY/2009/11
Table 5.12 Water
Monitoring Stations for Contract no. HK/2009/01
Table 5.13 Water
Monitoring Stations for Contract no. HK/2009/02
Table 5.14 Water
Monitoring Stations for Contract no. HK/2010/06
Table 5.15 Water
Monitoring Stations for Contract no. HY/2009/15
Table 5.16 Water
Monitoring Stations for Contract no. HY/2009/19
Table 5.17 Summary
of Water Quality Monitoring Exceedances in Reporting Month
Table 5.18 Summary
of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month
Table 5.19 Details of
Waste Disposal for Contract no. HK/2009/01
Table 5.20 Details of
Waste Disposal for Contract no. HK/2009/02
Table 5.21 Details of
Waste Disposal for Contract no. HY/2009/15
Table 5.22 Details of
Waste Disposal for Contract no. HK/2010/06
Table 5.23 Details of Waste
Disposal for Contract no. HY/2009/19
Table 8.1 Summary of
Environmental Inspections for Contract no. HK/2009/01
Table 8.2 Summary of
Environmental Inspections for Contract no. HK/2009/02
Table 8.3 Summary of
Environmental Inspections for Contract no. HY/2009/15
Table 8.4 Summary of
Environmental Inspections for Contract no. HK/2010/06
Table 8.5 Summary
of Environmental Inspections for Contract no. HY/2009/19
Table 9.1 Cumulative
Statistics on Complaints
Table 9.2 Cumulative
Statistics on Successful Prosecutions
Table 10.1 Construction
Activities and Recommended Mitigation Measures in Coming Reporting Month
lIST
OF FIGUREs
Figure 2.2 Project Organization Chart
Figure 2.3 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix 5.1 Monitoring Schedule for Reporting Month and Coming month
Appendix 5.2 Noise Monitoring Results and Graphical Presentations
Appendix 5.3 Air Quality Monitoring Results and Graphical Presentations, and Odour Patrol Results
Appendix 5.4 Water Quality Monitoring Results and Graphical Presentations
Appendix 5.4a Additional Dissolved Oxygen Monitoring Results
Appendix 5.5 Real-time Noise Monitoring Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Summary for Notification of Exceedance
Appendix 8.1 Construction Programme of Individual Contracts
Construction Activities for the Reported Period
¡P
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The
construction site was handed over to contractor HY/2009/19.
Marine Works (at Wan Chai)
¡P
Rockfilling for rock bund
across HKCEC Water Channel from Ch220 to Ch230 Reclamation of HKCEC3W within
HKCEC Water Channel
¡P
Installation of pipe pile
wall for demolition of existing seawall at
¡P
Demolition of Wan Chai West
Ferry Pier
¡P
Fabrication of 3 nos. of
precast concrete caisson seawall
Cross-Harbour Watermains Installation (CHA &
CHB) and Marine Works (at TST)
¡P
Rockfilling and rock
protection to cross-harbour watermains
¡P
Thrust block construction
for A16 & B16 and A17 & B17
¡P
Site area at
Fresh Watermains, Cooling Watermains and Salt
Watermains (On Land)
¡P
Mainlaying works at Zone
B1-5A, B2-1, B3-1, B4-3, B4-1A, B5-1(Switch Room), B5-3(Switch Room), A1-1,
A1-2, A1-3B, A2-2, A3-2A, A3-4B and Run-out of Renaissance Hotel
¡P
Mainlaying works and
subsequent reinstatement in Zone A4-2A and Zone A3-5B
¡P
Mainlaying works and part
of the carriageway reinstatement in Zone A3-2A.Heading No. H1 would be carried
out in the excavated trench as a jacking pit
¡P
Mainlaying works at Zone
A3-4B
¡P
Mainlaying works at Run-out
of Renaissance Hotel
¡P
Excavation works for
Heading No. H6c (Mainlaying works by trenchless method) and pipe laying works
¡P
Heading No. H1
¡P
Pipe laying works for
heading No. H6a
¡P
Mainlaying and chamber
construction works at the traffic island near junction of
¡P
Mainlaying works at
¡P
Trial pit at Zone X1-6 of
¡P
Pipe Laying works including
9 nos. cooling mains and 2 nos. cross harbour watermains at North Bank of HKCEC
Water Channel
¡P
Pipe Laying works including
9 nos. cooling mains and 2 nos. cross harbour watermains across E/D section
within HKCEC Water Channel
¡P
Pipe Laying works including
9 nos. cooling mains and 2 nos. cross harbour watermains across SCL section
within HKCEC Water Channel
¡P
Final cleaning, CCTV
inspection and pressure test for the 9 nos. cooling watermains
¡P
Modification work of PTI at
¡P
Modification work of bus
station at
¡P
Initial testing of the
pumping stations of P7 (GE/HC), P8 (SHK) and P9 (CRB)
¡P
Reinstatement at
¡P
Cooling mains installation
at west of Gate 1 inside ex-pet garden and the steel fixing of the damaged
thrust box was casted
¡P
Waterproofing membrane at roof
level of WSD Salt Water Pumping Station
¡P
E&M works at WSD Salt
Water Pumping Station
¡P
Cutting opening and
removing sheet pile of WSD receiving pit connecting to Wan Shing Street Intake
Culverts
¡P
Concreting of the
inspection chamber (1st lift) at salt water intake culvert Bay 20
¡P
Stripping of formwork and cement
mortar of tie holes for wall shaft inside salt intake culvert Bay 19b ~ Bay 24
¡P
Welding for the 1st layer
waling at salt water intake culvert Bay 9 to Bay 11 at WCR1
¡P
Concreting of pile caps of
Bay
¡P
Concreting of pile caps of
Bay
¡P
Cutting the opening of
sheet piles and saw cutting of D-wall & thrust wall between Launching Pit
and Jacking Pit
¡P
Placing concrete for
surround the HDPE pipe at Submarine Sewage Outfall Seaside Cofferdam
¡P
Placing of 25.5¢X
¡P
Placing of Mild Steel
Horizontal Bend at DSD Receiving Pit of pipeline A
¡P
Fixing brackets to the bend
section at temporary steel bridge
¡P
Laying HDPE pipes and
placing concrete surround for the pipes at Launching Pit & TBM Jacking Pit
¡P
Concreting the base slab of
Box Culvert N1 Bay 1
¡P
The wall & top slab of
Bay 2 and Bay 3 on UU bridge
¡P
Welding steel capping plate
for pile cap of Box N1 Bay 4, steel re-bars for pile cap
¡P
Welding steel capping plate
for pile cap of Box N1 Bay 5
¡P
TTA for trial excavation
and preparation works for Hung Hing Road Diversion
¡P
Dewatering for the
construction new Ø
¡P
Concreting the columns at
New Ferry Pier C8B to C
¡P
Concreting the column at
New Ferry Pier C10D and hanger wall between Level
¡P
Concreting the slab at New
Ferry Pier Level
¡P
Deep excavation works were
ongoing. The excavation levels have reached -20mPD to -23mPD on the eastern and
western portion of the site
¡P
Rockfilling and placing
bagged concrete for the temporary seawall at WCR2 Reclamation of WCR2
¡P
TZ1 reclamation works
¡P
Removal of temporary
reclamation at TS1
¡P
Dredging for seawall
foundation at TS2
¡P
Formation of temporary
seawall at TS2
¡P
Seawall trench works at TS2
¡P
Pile head breaking
¡P
Sonic tube trimming
¡P
Marine bored piling
¡P
Construction works for Box Culvert T
Real-time
Noise Monitoring
Air Quality Monitoring
CMA1b: from 6 and 24 September 2012 to 7 and 25
September 2012
CMA3a: from 18 September 2012 to 19 September 2012
CMA4a: from 24 September 2012 to 25 September 2012
CMA5a: from 31 August and 24 September 2012 to 1
and 26 September 2012
CMA6a: from 31 August 2012 to 1 September 2012
Water Quality Monitoring
Table I Summary of Water Quality Monitoring Exceedances in
Reporting Month
Contract
no. |
Water
Monitoring Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
|||||||||
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|||
HY/2009/11 |
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Monitoring finished on 6 Feb 2012 |
WSD10 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD15 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C8 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/01 |
WSD19 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C3 |
1 |
0 |
0 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
0 |
0 |
|
|
C4e |
0 |
0 |
0 |
0 |
0 |
0 |
3 |
0 |
0 |
0 |
0 |
0 |
|
|
C4w |
1 |
0 |
0 |
0 |
0 |
0 |
3 |
0 |
0 |
0 |
0 |
0 |
|
Monitoring finished on 27 April 2012 |
WSD20 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
HK/2009/01 & HK/2010/06 |
C2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/02 |
C5e |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
|
|
C5w |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Monitoring started on 8 Feb 2012 |
WSD21 |
1 |
0 |
0 |
0 |
0 |
0 |
2 |
2 |
0 |
0 |
0 |
0 |
|
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
||
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HY/2009/15 |
C7 |
1 |
1 |
0 |
0 |
0 |
0 |
3 |
0 |
0 |
0 |
0 |
0 |
|
HY/2009/19 Monitoring started on 28 Jan 2012 |
C8 |
0 |
0 |
1 |
0 |
1 |
0 |
1 |
0 |
0 |
1 |
0 |
0 |
|
C9 |
1 |
0 |
0 |
2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
Total |
6 |
1 |
1 |
2 |
1 |
0 |
14 |
3 |
0 |
1 |
0 |
1 |
||
Remarks: -
The
cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the
water monitoring at C6 was then terminated since 17 May 2011.
-
WSD9 and WSD17 were implemented with respect to HK/2009/02 from 8 Feb 2012.
- 4-week water quality monitoring at
WSD9, WSD10, WSD15, WSD17, C8 and C9 were completed on 6 Feb 2012.
- C8 and C9 were implemented with
respect to HY/2009/19 from 28 Jan 2012.
- WSD7 and WSD20 water quality
monitoring were temporarily suspended from 27 Apr 2012.
Table II Summary of Enhanced
Dissolved Oxygen Monitoring Exceedances in Reporting Month
Contract no. |
Water Monitoring Station |
Mid-flood |
Mid-ebb |
||
DO |
DO |
||||
|
LL |
|
LL |
||
HY/2009/15 |
C6 |
0 |
0 |
1 |
0 |
C7 |
1 |
1 |
2 |
1 |
|
Ex-WPCWA SW |
2 |
4 |
0 |
7 |
|
Ex-WPCWA SE |
4 |
4 |
2 |
8 |
|
Total |
7 |
9 |
5 |
16 |
Complaints, Notifications of Summons and Successful
Prosecutions
Site Inspections and Audit
Future Key Issues
Contract no. HY/2009/11- North Point
Reclamation
¡P
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The
construction site was handed over to contractor HY/2009/19 on 31 December 2011.
Contract no. HK/2009/01 - Wan Chai
Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC
Marine Works
¡P
Fabrication of 3 nos. precast concrete caisson
seawall was in progress and anticipated to be delivered to Site
¡P
Dredging works for Type 3 sediment underneath
¡P
Installation pipe pile wall for modification of
vertical seawall near
¡P
Rockfilling at east of HKCEC near
¡P
Trust block construction and rockfilling protection
works for cross-harbour watermains in
¡P
Reinstatement works at TST seashore including
removal of silt screen and demobilization of jack-up barge
Fresh
Watermains, Cooling Watermains and Salt Watermains (On Land)
¡P
Zone B1-5A, B2-1, B5-1(Switch Room), B5- 3(Switch
Room), A1-1, A1-2, A2-2, A3-2A, A3-4B, run-out of Renaissance Hotel and C1-10
¡P
Mainlaying works at Zone C1-10 and run-out of
Renaissance Hotel
¡P
Reinstatement works at Zone B4-3 and B4-1A
¡P
Mainlaying works at
¡P
Mainlaying works at
¡P
Workfront at Zone A1-4 (CHWM)
¡P
Mainlaying works at traffic island near junction
between
¡P
Mainlaying works at Zone A3-4B, A3-4A & A3-5A,
Zone A3-4B
¡P
Pipe laying works for cross harbour watermains
across HKCEC water channel
¡P
Final cleaning, CCTV inspection and pressure test
for the 9 nos. cooling watermains
Contract no. HK/2009/02 - Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
¡P
Commence drainage diversion works to suit TWCR4
construction.
¡P
Complete diversion of uncharted drainage works at
Box culvert ¡§O¡¨.
¡P
Commence trial excavation and preparation works for
Hung Hing Road Diversion
¡P
Commence caisson seawall precast unit 2X in-situ
work on flat-top barge.
¡P
Commence seawall strengthening works at WCR2 area.
¡P
Complete PTI modification works after completion of
New Public Toilet in
¡P
Complete all cooling mains and cabling works for P7,
P8 & P9 Pumping Stations permanent power-on and signal control.
¡P
Continue 800MS pipe installation inside Ex-pet
Garden.
¡P
Conduct Fire Service Inspection of WSD Salt Water Pumping Station on 27 Sept
2012
¡P
Complete the finishing works of WSD Salt Water
Pumping Station.
¡P
Continue construction of Bay 1b ¡V 2, Bay 6 ¡V 8 salt
water intake culverts at WCR1 area.
¡P
Complete ELS of the salt water intake
¡P
Continue salt water intake culvert at transition
bays inside jacking pit and receiving pit.
¡P
Continue remaining drainage works and reinstatement
works along
¡P
Continue HDPE piping on UU Bridge and inside
outfall seaside cofferdam.
¡P
Continue construction for Box Culvert N1 at WCR1
area.
¡P
Complete concreting works for the Level 2 at the
New Ferry Pier.
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V
Tunnel (
¡P
TZ1 reclamation works
¡P
Seawall trench works at TS2
¡P
Formation of temporary seawall at TS2
¡P
Pile head breaking
¡P
Platform Disassembly
¡P
Sonic tube trimming
Contract no. HY/2009/19- Wan Chai
Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
¡P
Construction works for Box Culvert T
¡P
Marine Piling
¡P
Construction of 1500f drainage pipe
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to
work as the Environmental Team (ET) under Environmental Permit no. EP-356/2009
and Further Environmental permit nos. FEP-01/356/2009, FEP-02/356/2009,
FEP-03/356/2009, FEP-04/356/2009 and FEP-05/356/2009 to implement the Environmental
Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual
of the approved Environmental Impact Assessment (EIA) Report for Wan Chai
Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008)
and in the EM&A Manual of the approved EIA Report for Central-Wan Chai
Bypass and Island Eastern Corridor Link (Register No. AEIAR-014/2001).
1.1.2.
This report presents the environmental monitoring
and auditing work carried out in accordance to the Section 10.3 of EM&A
Manual and ¡§Environmental Monitoring and Audit Requirements¡¨ under
Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A works
for Environmental Permit no. EP-356/2009, Further Environmental Permit no.
FEP-01/356/2009, FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009 and
FEP-05/356/2009 and during the period of
August to September. The cut-off
date of reporting is at 27th of each reporting month.
Section 1 Introduction ¡V details the
scope and structure of the report.
Section 2 Project
Background ¡V summarizes background and scope of the project, site
description, project organization and contact details of key personnel during
the reporting period.
Section 3 Status of Regulatory Compliance ¡V summarizes the
status of valid Environmental Permits / Licenses during the reporting period.
Section 4 Monitoring
Requirements ¡V summarizes all monitoring parameters, monitoring
methodology and equipment, monitoring locations, monitoring frequency, criteria
and respective event and action plan and monitoring programmes.
Section 5 Monitoring
Results ¡V summarizes the monitoring results obtained in the
reporting period.
Section 6 Compliance Audit ¡V summarizes the auditing of monitoring results, all exceedances
environmental parameters.
Section 7 Cumulative Construction Impact due to the Concurrent Projects ¡V summarizes the relevant cumulative construction impact due to the
concurrent activities of the concurrent Projects.
Section 8 Site Inspection ¡V summarizes the findings of weekly site
inspections undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.
Section 9 Complaints, Notification of summons and Prosecution ¡V summarizes the cumulative statistics on complaints, notification of summons and
prosecution
Section 10 Conclusion
2.1.1.
¡§Wan Chai Development phase II and Central-Wan Chai
Bypass¡¨ and ¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨
(hereafter called ¡§the Project¡¨) are Designed Project (DP) under the
Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental
Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The key purpose of Wan Chai Development Phase II
(WDII) is to provide land at Wan Chai North and North Point for construction of
the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed
under the project will be developed as a world-class waterfront promenade
joining that at the new Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB
to provide relief to the very congested
2.2.1.
The Project is located mainly in Wan Chai North,
2.2.2.
The study area encompasses existing developments
along the Wan Chai,
2.2.3.
The scope of the Project comprises:
¡P
Land
formation for key transport infrastructure and facilities, including the Trunk
Road (i.e.
CWB) and the associated slip roads for connection to the Trunk Road and for through
traffic from Central to Wan Chai and Causeway Bay. The land formed for the above
transport infrastructure will provide opportunities for the development of an
attractive waterfront promenade for the enjoyment of the public
¡P
Reprovisioning
/ protection of the existing facilities and structures affected by the land
formation works mentioned above
¡P
Extension,
modification, reprovisioning or protection of existing storm water drainage
outfalls, sewerage outfalls and watermains affected by the revised land use and
land formation works mentioned above
¡P
Upgrading
of hinterland storm water drainage system and sewerage system, which would be
rendered insufficient by the land formation works mentioned above
¡P
Provision
of the ground level roads, flyovers, footbridges, necessary transport
facilities and the associated utility services
¡P
Construction
of the new waterfront promenade, landscape works and the associated utility
services
¡P
The
Trunk Road (i.e. CWB) within the study area and the associated slip roads for
connection to the Trunk Road.
2.2.4.
The project also contains various Schedule 2 DPs
that, under the EIAO, require Environmental Permits (EPs) to be granted by the
DEP before they may be either constructed or operated. Table 2.1
summarises the five individual DPs under this Project. Figure 2.1 shows the
locations of these Schedule 2 DPs.
Table 2.1 Schedule
2 Designated Projects under this Project
Item |
Designated
Project |
EIAO
Reference |
Reason for
inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project,
there are a number of contracts sub-dividing the whole works area into
different work areas to be commenced. Contractors of individual contracts will
be required by the EP holder to apply Further Environmental Permits (FEP) such
that the impact monitoring stations are sub-divided accordingly to facilitate
the implementation of EM&A programme and to streamline the EM&A
reporting for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are summarized
in Table 2.2.
Table 2.2 Details
of Individual Contracts under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HK/2009/01 |
Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at |
DP3, DP6 |
23 July 2010 |
DP1, DP2 |
25 August 2011 |
||
HK/2009/02 |
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai
East |
DP3, DP5 |
5 July 2010 |
DP1 |
26 April 2011 |
||
HY/2009/11 |
Wan Chai Development Phase II and Central ¡V Wan Chai Bypass ¡V North
Point Reclamation |
DP3 |
17 March 2010 (Under application of surrender) |
HY/2009/15 |
Central-Wanchai Bypass ¡V Tunnel ( |
DP3 |
10 November 2010 |
DP1 |
13 July 2011 |
||
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 |
HY/2009/17 |
Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central - Wan Chai Bypass (CWB) ¡V Central Interchange |
DP1 |
21 April 2011 |
HY/2009/19 |
Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the
construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The proposed project organization and lines of
communication with respect to environmental protection works are shown in Figure
2.2. Key personnel
and contact particulars are summarized in Table 2.3:
Table 2.3 Contact Details of
Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer¡¦s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer¡¦s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3912 3388 |
3912 3010 |
|
|
Contractor under Contract no. HY/2009/11 |
Project Director |
Mr. Cho Yu Fun |
3157 1086 |
3157 1085 |
Project
Manager |
Mr. Gregory Wong |
3157 1086 |
|||
Site Agent |
Mr. Daniel Cheung |
3157 1086 |
|||
Environmental
Officer |
Mr. C. M. Wong |
3157 1086 |
|||
Chun Wo ¡V Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Project Director |
|
2162 9909 |
2587 1878 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Sub-Agent |
Mr Terry Wong |
9757 9846 |
|||
Construction
Manager |
Mr. Wyman
Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack Chu |
9775 3008 |
|||
Construction
Manager |
Mr. KK Yuen |
9498 1213 |
|||
Environmental
Officer (Compliance Manager) |
Mr. Andy Mak |
9103 2370 |
|||
Chun Wo ¡V CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. Chan Sing Cho |
3658 3002 |
2827 9996 |
Quality & Environmental Manager |
Mr. C.P. Ho |
3658 3000 |
|||
|
Contractor under Contract no. HY/2009/15 |
Project Director |
Chan Wai Hung |
2823 7813 |
2865 5229 |
Site Manager |
P J Fan |
3557 6368 |
2566 2192 |
||
|
|
Contractor¡¦s Representative |
Mr. David Lau |
3557 6358 |
|
|
|
Head of Construction Manager |
Roger Cheung |
3557 6371 |
|
|
|
Senior Construction Manager |
Gene Cheung |
3557 6395 |
|
|
|
Environmental Officer |
Mr. Daniel Sin |
3557 6347 |
|
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project
Manager |
Mr. Paul Lui |
9095 7922 |
2529 2880 |
Site Agent |
Mr. Keith Tse |
2529 2068 |
|||
Environmental
Officer |
Mr. Lee Wai Man |
9481 6024 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Site Agent |
Mr. Cheung Kit Cheung |
6909 1555 |
|||
Environmental
Engineer |
Mr. Calvin Leung |
9286 9208 |
|||
Environmental Manager / Environmental
Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Construction Manager (Marine) |
William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
Construction Manager (Land) |
Eric Fong |
6191 9337 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
For Contract no. HY/2009/11, the principal work
activities in this reporting month included:
¡P
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The
construction site was handed over to contractor HY/2009/19
on 31 December 2011.
2.4.4.
For Contract no. HK/2009/01, the principal work
activities in this reporting month included:
Marine Works
(at Wan Chai)
¡P
Rockfilling for rock bund
across HKCEC Water Channel from Ch220 to Ch230 Reclamation of HKCEC3W within
HKCEC Water Channel
¡P
Installation of pipe pile
wall for demolition of existing seawall at
¡P
Demolition of Wan Chai West
Ferry Pier
¡P
Fabrication of 3 nos. of
precast concrete caisson seawall
Cross-Harbour
Watermains Installation (CHA & CHB) and Marine Works (at TST)
¡P
Rockfilling and rock
protection to cross-harbour watermains
¡P
Thrust block construction
for A16 & B16 and A17 & B17
¡P
Site area at
Fresh
Watermains, Cooling Watermains and Salt Watermains (On Land)
¡P
Mainlaying works at Zone
B1-5A, B2-1, B3-1, B4-3, B4-1A, B5-1(Switch Room), B5-3(Switch Room), A1-1,
A1-2, A1-3B, A2-2, A3-2A, A3-4B and Run-out of Renaissance Hotel
¡P
Mainlaying works and
subsequent reinstatement in Zone A4-2A and Zone A3-5B
¡P
Mainlaying works and part
of the carriageway reinstatement in Zone A3-2A.Heading No. H1 would be carried
out in the excavated trench as a jacking pit
¡P
Mainlaying works at Zone
A3-4B
¡P
Mainlaying works at Run-out
of Renaissance Hotel
¡P
Excavation works for
Heading No. H6c (Mainlaying works by trenchless method) and pipe laying works
¡P
Heading No. H1
¡P
Pipe laying works for
heading No. H6a
¡P
Mainlaying and chamber
construction works at the traffic island near junction of
¡P
Mainlaying works at
¡P
Trial pit at Zone X1-6 of
¡P
Pipe Laying works including
9 nos. cooling mains and 2 nos. cross harbour watermains at North Bank of HKCEC
Water Channel
¡P
Pipe Laying works including
9 nos. cooling mains and 2 nos. cross harbour watermains across E/D section
within HKCEC Water Channel
¡P
Pipe Laying works including
9 nos. cooling mains and 2 nos. cross harbour watermains across SCL section
within HKCEC Water Channel
¡P
Final cleaning, CCTV
inspection and pressure test for the 9 nos. cooling watermains
2.4.5.
For Contract no. HK/2009/02, the principal work
activities in this reporting month included:
¡P
Modification work of PTI at
¡P
Modification work of bus
station at
¡P
Initial testing of the
pumping stations of P7 (GE/HC), P8 (SHK) and P9 (CRB)
¡P
Reinstatement at
¡P
Cooling mains installation
at west of Gate 1 inside ex-pet garden and the steel fixing of the damaged
thrust box was casted
¡P
Waterproofing membrane at roof
level of WSD Salt Water Pumping Station
¡P
E&M works at WSD Salt
Water Pumping Station
¡P
Cutting opening and
removing sheet pile of WSD receiving pit connecting to Wan Shing Street Intake
Culverts
¡P
Concreting of the
inspection chamber (1st lift) at salt water intake culvert Bay 20
¡P
Stripping of formwork and cement
mortar of tie holes for wall shaft inside salt intake
¡P
Welding for the 1st layer
waling at salt water intake culvert Bay 9 to Bay 11 at WCR1
¡P
Concreting of pile caps of
Bay
¡P
Concreting of pile caps of
Bay
¡P
Cutting the opening of
sheet piles and saw cutting of D-wall & thrust wall between Launching Pit
and Jacking Pit
¡P
Placing concrete for
surround the HDPE pipe at Submarine Sewage Outfall Seaside Cofferdam
¡P
Placing of 25.5¢X
¡P
Placing of Mild Steel
Horizontal Bend at DSD Receiving Pit of pipeline A
¡P
Fixing brackets to the bend
section at temporary steel bridge
¡P
Laying HDPE pipes and
placing concrete surround for the pipes at Launching Pit & TBM Jacking Pit
¡P
Concreting the base slab of
Box Culvert N1 Bay 1
¡P
The wall & top slab of
Bay 2 and Bay 3 on UU bridge
¡P
Welding steel capping plate
for pile cap of Box N1 Bay 4, steel re-bars for pile cap
¡P
Welding steel capping plate
for pile cap of Box N1 Bay 5
¡P
TTA for trial excavation
and preparation works for Hung Hing Road Diversion
¡P
Dewatering for the
construction new Ø
¡P
Concreting the columns at
New Ferry Pier C8B to C
¡P
Concreting the column at
New Ferry Pier C10D and hanger wall between Level
¡P
Concreting the slab at New
Ferry Pier Level
¡P
Deep excavation works were
ongoing. The excavation levels have reached -20mPD to -23mPD on the eastern and
western portion of the site
¡P
Rockfilling and placing
bagged concrete for the temporary seawall at WCR2 Reclamation of WCR2
2.4.6.
For Contract no. HY/2009/15, the principal work
activities in this reporting month included:
¡P
TZ1 reclamation works
¡P
Removal of temporary
reclamation at TS1
¡P
Dredging for seawall
foundation at TS2
¡P
Formation of temporary
seawall at TS2
¡P
Seawall trench works at TS2
2.4.7.
For Contract no. HK/2010/06, the principal work
activities in this reporting month included:
¡P
Pile head breaking
¡P
Sonic tube trimming
2.4.8.
For Contract no. HY/2009/19, the principal work
activity in this reporting month included:
¡P
Marine bored piling
¡P
Construction works for Box
Culvert T
2.4.9.
In coming reporting month, the principal work
activities of individual contracts are anticipated as follows:
Contract no. HY/2009/11- North Point
Reclamation
¡P
The
major work activities for Contract no. HY/2009/11 was confirmed substantial
complete by RSS on 4 January 2012. The construction site was handed over to contractor HY/2009/19 on 31 December
2011.
Contract no. HK/2009/01 - Wan Chai
Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC
Marine Works
¡P
Fabrication of 3 nos. precast concrete caisson
seawall was in progress and anticipated to be delivered to Site
¡P
Dredging works for Type 3 sediment underneath
¡P
Installation pipe pile wall for modification of
vertical seawall near
¡P
Rockfilling at east of HKCEC near
¡P
Trust block construction and rockfilling protection
works for cross-harbour watermains in
¡P
Reinstatement works at TST seashore including
removal of silt screen and demobilization of jack-up barge
Fresh
Watermains, Cooling Watermains and Salt Watermains (On Land)
¡P
Zone B1-5A, B2-1, B5-1(Switch Room), B5- 3(Switch
Room), A1-1, A1-2, A2-2, A3-2A, A3-4B, run-out of Renaissance Hotel and C1-10
¡P
Mainlaying works at Zone C1-10 and run-out of
Renaissance Hotel
¡P
Reinstatement works at Zone B4-3 and B4-1A
¡P
Mainlaying works at
¡P
Mainlaying works at
¡P
Workfront at Zone A1-4 (CHWM)
¡P
Mainlaying works at traffic island near junction
between
¡P
Mainlaying works at Zone A3-4B, A3-4A & A3-5A,
Zone A3-4B
¡P
Pipe laying works for cross harbour watermains
across HKCEC water channel
¡P
Final cleaning, CCTV inspection and pressure test
for the 9 nos. cooling watermains
Contract no.
HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai
East
¡P
Commence drainage diversion works to suit TWCR4
construction.
¡P
Complete diversion of uncharted drainage works at
Box culvert ¡§O¡¨.
¡P
Commence trial excavation and preparation works for
Hung Hing Road Diversion
¡P
Commence caisson seawall precast unit 2X in-situ
work on flat-top barge.
¡P
Commence seawall strengthening works at WCR2 area.
¡P
Complete PTI modification works after completion of
New Public Toilet in
¡P
Complete all cooling mains and cabling works for P7,
P8 & P9 Pumping Stations permanent power-on and signal control.
¡P
Continue 800MS pipe installation inside
¡P
Conduct Fire Service Inspection of WSD Salt Water Pumping Station on 27 Sept
2012
¡P
Complete the finishing works of WSD Salt Water
Pumping Station.
¡P
Continue construction of Bay 1b ¡V 2, Bay 6 ¡V 8 salt
water intake culverts at WCR1 area.
¡P
Complete ELS of the salt water intake
¡P
Continue salt water intake culvert at transition
bays inside jacking pit and receiving pit.
¡P
Continue remaining drainage works and reinstatement
works along
¡P
Continue HDPE piping on UU Bridge and inside
outfall seaside cofferdam.
¡P
Continue construction for Box Culvert N1 at WCR1
area.
¡P
Complete concreting works for the Level 2 at the
New Ferry Pier.
Contract no. HY/2009/15 -
Central-Wanchai Bypass ¡V Tunnel (
¡P
TZ1 reclamation works
¡P
Seawall trench works at TS2
¡P
Formation of temporary seawall at TS2
Contract no. HK/2010/06 - Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line
¡P
Pile head breaking
¡P
Platform Disassembly
¡P
Sonic tube trimming
Contract no. HY/2009/19 ¡V Central- Wan
Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
¡P
Construction
works for Box Culvert T
¡P
Marine
Piling
¡P
Construction
of 1500f
drainage pipe
3.1.1.
A summary of the current status on licences and/or
permits on environmental protection pertinent to the Project is shown in Table
3.1.
Permits and/or
Licences |
Reference No. |
Issued Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental
Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Under application of surrender |
Further Environmental
Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental
Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-04/356/2009 |
22 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-05/356/2009 |
24 Mar 2011 |
Valid |
Further Environmental Permit |
FEP-01/364/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-02/364/2009 |
21 Apr 2010 |
Valid |
Further Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
Valid |
Further Environmental Permit |
FEP-04/364/2009/A |
14 Oct 2010 |
Surrendered |
Further Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-06/364/2009/A |
22 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-07/364/2009/A |
25 Feb 2011 |
Valid |
Further Environmental Permit |
FEP-08/364/2009/A |
15 Jun 2012 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project,
the status of permits and/or licences under the individual contract(s) are
presented as below:
Contract no. HY/2009/11 ¡V
Central ¡V Wanchai Bypass, North Point Reclamation
3.1.3.
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The
construction site was handed over to contractor HY/2009/19 on 31 December 2011.
3.1.4.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission under
FEP-01/356/2009 for contract no. HY/2009/11 are shown in Table 3.2 and
Table 3.3.
3.1.5.
Contractor submitted a letter dated 20 July 2011 to
confirm that the dredging works and dumping operation were completed.
Table 3.2 Cumulative Summary of Valid Licences and
Permits under Contract
no. HY/2009/11
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
N/A |
Valid |
Notification of Works Under APCO |
331892 |
4 Jul. 2011 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-151-C3631-02 |
12 Oct 2010 |
N/A |
Valid |
Billing Account under Waste Disposal Ordinance |
7010037 |
13 Jan 2010 |
N/A |
Valid |
Discharge Licence |
WT00007942-2010 |
29 Nov 2010 |
30 Nov 2015 |
Valid |
Table 3.3 Summary of
submission status under FEP-01/356/2009 Condition
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management
Organization of Main Construction Companies |
18 Dec 2009 |
Condition 2.7 |
Submission of works
schedule and location plan |
8 Feb 2010 |
Condition 2.8 |
Revised Silt
Curtain Deployment Plan (Rev. 3) |
4 Dec 2010 |
Condition 2.9 |
Silt Screen
Deployment Plan (Rev. 6) |
18 May 2011 |
Condition 2.10 |
Coral Translocation
Plan |
20 Nov 2009 |
Condition 2.16 |
Revised Noise
Management Plan (Rev 5) |
19 Feb 2011 |
Condition 2.17 |
Landscape Plan |
12 May 2010 |
|
Revised landscape
Plan |
30 Jun 2010 |
|
Submission of
Supplementary Information - Revised Management & Maintenance Schedule for
Submitted Revised Landscape Plan |
25 Aug 2010 |
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
3.1.6.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission for contract no.
HK/2009/01 under FEP-02/356/2009 are shown in Table 3.4 and
Table 3.5.
Table 3.4 Cumulative Summary
of Valid Licences and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
313088 |
6 Jan 2010 |
N/A |
Valid |
Construction Noise
Permit (CNP) for non-piling equipment |
GW-RS0225-12 |
2 Mar 2012 |
14 Mar 2011 to 13 Sep 2012 |
Expired |
|
GW-RS0227-12 |
2 Mar 2012 |
16 Mar 2011 to 15 Sep 2012 |
Expired |
|
GW-RE0174-12 |
5 Mar 2012 |
30 Mar 2012 to 29 Sep 2012 |
Valid |
|
GW-RS0356-12 |
03 Apr 2012 |
11 Apr 2012 to 29 Sep 2012 |
Valid |
|
GW-RS0394-12 |
16 Apr 2012 |
19 Apr 2012 to 12 Oct 2012 |
Valid |
|
GW-RS0806-12 |
3 Aug 2012 |
4 Aug 2012 to 03 Feb
2013 |
Valid |
|
GW-RS0823-12 |
3 Aug 2012 |
3 Aug 2012 to 02 Feb 2013 |
Valid |
|
GW-RS0852-12 |
16 Aug 2012 |
16 Aug 2012 to 01 Feb
2013 |
Valid |
|
GW-RS0312-12 |
28 Mar 2012 |
30 Mar 2012 to 29 Sep 2012 |
Cancelled |
GW-RS0855-12 |
16 Aug 2012 |
17 Aug 2012 to 9 Feb 2013 |
Valid |
|
GW-RS0862-12 |
20 Aug 2012 |
28 Aug 2012 to 27 Feb 2013 |
Valid |
|
GW-RS0949-12 |
12 Sep 2012 |
16 Sep 2012 to 15 Mar 2013 |
Valid |
|
GW-RS0545-12 |
24 May 2012 |
26 May 2012 to 25 Nov 2012 |
Valid |
|
GW-RS0546-12 |
25 May 2012 |
26 May 2012 to 25 Nov 2012 |
Valid |
|
GW-RS0460-12 |
10 May 2012 |
13 May 2012 to 6 Nov 2012 |
Valid |
|
|
GW-RS0514-12 |
14 May 2012 |
27 May 2012 to 26 Nov 2012 |
Valid |
GW-RS0760-12 |
18 Jul 2012 |
20 Jul 2012 to 19 Jan 2013 |
Valid |
|
GW-RS0771-12 |
23 Jul 2012 |
23 Jul 2012 to 31 Aug 2012 |
Expired |
|
GW-RS0994-12 |
25 Sep 2012 |
25 Sep 2012 to 19 Nov 2012 |
Valid |
|
GW-RS1011-12 |
26 Sep 2012 |
30 Sep 2012 to 29 Mar 2013 |
Valid |
|
GW-RS1017-12 |
27 Sep 2012 |
30 Sep 2012 to 24 Mar 2013 |
Valid |
|
GW-RE0793-12 |
21 Sep 2012 |
30 Sep 2012 to 29 Mar 2013 |
Valid |
|
Discharge Licence |
WT00006220-2010 |
18 Mar 2010 |
31 Mar 2015 |
Valid |
|
WT00009641-2011 |
24 Jul 2011 |
31 Jul 2016 |
Valid |
Billing account under Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Dumping Permit (Type 1 ¡V |
EP/MD/13-004 |
23 May 2012 |
24 May 2012 to 23 Nov 2012 |
Valid |
Permit for Dumping at Sea - Dredged Sediment
Requiring Type 3 ¡V Special Treatment / Disposal contained in Geosynthetic
Containers |
EP/MD/13-061 |
4 Sep 2012 |
17 Sep 2012
to 16 Oct 2012 |
Valid |
Table 3.5 Summary of
submission status under FEP-02/356/2009 Condition
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main Construction Companies |
13 Apr 2010 |
Condition 2.7 |
Works Schedule and
Location Plan |
8 Apr 2010 |
Condition 2.8 |
Silt Curtain
Deployment Plan (Rev. 5) |
24 Aug 2012 |
Silt Curtain
Deployment Plan (Rev. 4) |
12 July
2012 |
|
Condition 2.9 |
Silt Screen
Deployment Plan |
19 Apr 2010 |
Conditions 2.8 and
2.9 |
Supplementary
Document on Silt Curtain and Silt Screen Deployment Plan |
19 Jul 2010 |
Report on Field
Testing for Silt Curtain |
26 Aug 2010 |
|
Report on Field
Testing for Silt Curtain (Rev. A) |
15 Nov 2010 |
|
Condition 2.12(d) |
Alternative Proposal
on Concurrent Dredging for Sewage Pipeline and |
15 Apr 2011 |
Condition 2.17 |
Noise Management
Plan |
23 Apr 2010 |
Condition 2.18 |
Landscape Plan
(Erection of Decorative Screen Hoarding along Construction Site around |
15 May 2010 |
|
Landscape Plan
(Night-time Lighting) |
22 Oct 2010 |
|
Landscape Plan (Rev.
B) |
15 Nov 2010 |
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
3.1.7.
Summary of the current status
on licences and/or permits on environmental protection pertinent and submission
for contract no. HK/2009/02 under FEP-03/356/2009 are shown in Table 3.6 and
Table 3.7.
Table 3.6 Cumulative Summary
of Valid Licences and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
|
|
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
Notification of Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for piling
equipment |
PP-RS0007-12 |
27 Mar 2012 |
28 Mar 2012
to 27 Sept 2012 |
Cancelled |
Construction Noise Permit (CNP) for non-piling
equipment |
GW-RS0671-12 |
25 June 2012 |
17 Jul 2012 to 16 Jan 2013 |
Valid |
|
GW-RS0730-12 |
9 July 2012 |
10 Jul 2012 to 8 Jan 2013 |
Valid |
|
GW-RS0736-12 |
9 July 2012 |
9 Jul 2012 to 8 Jan
2013 |
Valid |
|
GW-RS0255-12 |
14 Mar 2012 |
17 Mar 2012 to 15 Sept 2012 |
Valid |
|
GW-RE0283-12 |
5 Apr 2012 |
1 May 2012 to 30 Nov 2012 |
Valid |
|
GW-RS0739-12 |
9 July 2012 |
1 Aug 2012 to 31 Jan 2013 |
Valid |
|
GW-RS0301-12 |
20 Mar 2012 |
21 Mar 2012 to 20 Sept 2012 |
Cancelled |
|
GW-RS0303-12 |
26 Mar 2012 |
27 Mar 2012 to 27 Sept 2012 |
Valid |
|
GW-RS0341-12 |
3 Apr 2012 |
28 Apr 2012 to 27 Oct 2012 |
Valid |
|
GW-RS0348-12 |
3 Apr 2012 |
10 Apr 2012 to 9 Oct 2012 |
Valid |
|
GW-RS0380-12 |
12 Apr 2012 |
1 May 2012 to 31 Oct 2012 |
Valid |
|
GW-RS0388-12 |
13 Apr 2012 |
1 May 2012 to 31 Oct 2012 |
Valid |
|
GW-RS0418-12 |
30 Apr 2012 |
23 May 2012 to 22 Nov 2012 |
Valid |
|
GW-RS0420-12 |
30 Apr 2012 |
18 May 2012 to 17 Nov 2012 |
Cancelled |
|
GW-RS0423-12 |
30 Apr 2012 |
19 May 2012 to 18 Nov 2012 |
Cancelled |
|
GW-RS0427-12 |
30 Apr 2012 |
23 May 2012 to 22 Nov 2012 |
Valid |
|
GW-RS0445-12 |
30 Apr 2012 |
1 May 2012 to 25 Sept 2012 |
Expired |
GW-RS0533-12 |
21 May 2012 |
21 May 2012 to 10 Nov 2012 |
Valid |
|
GW-RS0550-12 |
25 May 2012 |
7 June 2012 to 6 Dec 2012 |
Valid |
|
GW-RS0611-12 |
14 June 2012 |
15 Jun 2012 to 28 Nov 2012 |
Valid |
|
GW-RS0611-12 |
14 June 2012 |
15 Jun 2012 to 28 Nov 2012 |
Valid |
|
GW-RS0633-12 |
13 June 2012 |
16 Jun 2012 to 14 Dec 2012 |
Valid |
|
GW-RS0814-12 |
3 Aug 2012 |
6 Aug 2012 to 5 Dec 2012 |
Valid |
|
GW-RS0850-12 |
10 Aug 2012 |
14 Aug 2012 to 13 Feb 2013 |
Valid |
|
GW-RS0870-12 |
21 Aug 2012 |
16 Sept 2012 to 31 Dec 2012 |
Valid |
|
GW-RS0996-12 |
25 Sept 2012 |
26 Sept 2012 to 25 Mar 2013 |
Valid |
|
Discharge Licence |
WT00006249-2010 |
22 Mar 2010 |
31 Mar 2015 |
Valid |
|
WT00006436-2010 |
15 Apr 2010 |
30 Apr 2015 |
Valid |
WT00006673-2010 |
14 May 2010 |
31 Mar 2015 |
Cancelled |
|
WT00006757-2010 |
28 May 2010 |
31 May 2015 |
Valid |
|
WT00007129-2010 |
28 July 2010 |
31 Jul 2015 |
Valid |
|
WT00008982-2011 |
26 April 2011 |
30 April 2016 |
Valid |
|
WT00009691-2011 |
1 Aug 2011 |
31 July 2016 |
Valid |
|
Billing Account under Waste Disposal Ordinance (Land) |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Billing Account under Waste Disposal Ordinance (Marine) |
7011496 |
6 Oct 2010 |
N/A |
Valid |
Registration as Chemical Waste Producer (Wan Chai) |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Registration as Chemical Waste Producer (TKO 137) |
WPN5213-839-C3593-02 |
22 Sep 2010 |
N/A |
Valid |
Dumping Permit (Type 1 ¡V |
EP/MD/13015 |
25 May 2012 |
29 May 2012 to 28 Nov 2012 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type
2 ¡V Confined Marine disposal) |
EP/MD/13-046 |
27 July 2012 |
6 Aug 2012 to 5 Sept 2012 |
Expired |
|
EP/MD/13-058 |
29 Aug 2012 |
6 Sep 2012 to 5 Oct 2012 |
Valid |
Table 3.7 Summary of
submission status under FEP-03/356/2009 Condition
EP Condition |
Submission |
Date of Submission |
Condition 1.12 |
Commencement Date of
Construction of Marine Works |
8 April 2010 |
Condition 2.6 |
Management
Organization of Main Construction Companies |
10 April 2010 |
Condition 2.7 |
Works Schedule and
Location Plans |
8 April 2010 |
Condition 2.8 |
Silt Curtain
Deployment Plan (Revision A) |
20 April 2010 |
Silt Curtain
Deployment Plan (Revision B) |
25 May 2010 |
|
Silt Curtain
Deployment Plan (Revision C) |
14 Jun 2010 |
|
Silt Curtain
Deployment Plan (Revision H) |
15 Feb 2011 |
|
Silt Curtain
Deployment Plan (Revision I) |
17 Nov 2011 |
|
Silt Curtain
Deployment Plan (Revision J) |
15 Feb 2012 |
|
Silt Curtain
Deployment Plan (Revision K) |
3 May 2012 |
|
Condition 2.9 |
Silt Screen
Deployment Plan |
21 April 2010 |
Supplementary
Information for Existing WSD Salt Water Intakes at |
5 Oct 2010 |
|
Silt Screen
Deployment Plan (Revision B) |
15 Feb
2012 |
|
Silt Screen
Deployment Plan (Revision C) |
3 May 2012 |
|
Condition 2.17 |
Noise Management
Plan |
6 May 2010 |
Condition 2.18 |
Landscape Plan
(Decorative Screen Hoarding) |
11 May 2010 |
Landscape Plan
(Control of Night Time Lighting) |
2 June 2010 |
|
|
Landscape Plan
(Combined Version) |
20 July 2011 |
Landscape Plan
(Combined Version) |
5 Aug 2011 |
|
----- |
Acknowledge of
Submission |
22 Aug 2011 |
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V
Tunnel (
3.1.8.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission for contract no.
HY/2009/15 under EP-356/2009 are shown in Table 3.8 and
Table 3.9.
Table 3.8 Cumulative Summary
of Valid Licences and Permits under Contract no. HY/2009/15
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental Permit |
FEP-04/356/2009 |
22 Nov 2010 |
N/A |
Valid |
FEP-06/364/2009/A |
22 Nov 2010 |
N/A |
Valid |
|
FEP-01/416/2011 |
11 Nov 2011 |
N/A |
Valid |
|
Notification of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Construction Noise
Permit (CNP) for Filling and Diaphragm Wall Works at TS4/ME4 |
GW-RS0249-12 |
10 Feb 2012 |
9 Mar 2012 to
31 Aug 2012 |
Expired |
GW-RS0924-12 |
31 Aug 2012 |
01 Sep 2012
to 28 Feb 2013 |
Valid |
|
Construction Noise
Permit (CNP) for non-piling equipment |
GW-RS0343-12 |
12 Apr 2012 |
13 Apr 2012
to 8 Oct 2012 |
Valid |
Construction Noise
Permit (CNP) for Removal Works at TS1 |
GW-RS0607-12 |
12 Jun 2012 |
13 Jun 2012
to 7 Dec 2012 |
Valid |
Registration as a
Chemical Waste Producer |
WPN5213-147-C1169-35 |
15 Nov 2010 |
N/A |
Valid |
Billing Account under Waste Disposal Ordinance |
7011553 |
30 Sep 2010 |
27 Sep 2010 to 27 Jan 2016 |
Valid |
Billing Account under Waste Disposal Ordinance
(Dumping by Vessel) |
7011761 |
10 Jul 2012 |
17 Jul 2012 to 16 Oct 2012 |
Valid |
Dumping Permit (Type 1 ¡V |
EP/MD/13-018 |
6 Jun 2012 |
6 Jun 2012 to
5 Dec 2012 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate
Sites) & Type 2 ¡V Confined Marine disposal) |
EP/MD/13-048 |
30 Jul 2012 |
8 Aug 2012 to 7 Sep 2012 |
Expired |
EP/MD/13-059 |
31 Aug 2012 |
8 Sep 2012 to 7 Oct 2012 |
Valid |
Table 3.9 Summary of
submission status under FEP-04/356/2009 Condition
FEP Condition |
Submission |
Date of Submission |
Condition 2.7 |
Works Schedule and Location Plans |
27 Oct 2010 |
|
Amendment for Works Schedule and Location Plans |
12 Nov 2010 |
Condition 2.8 |
Silt Curtain Deployment Plan |
30 Nov 2010 |
|
Amendment for Silt Curtain Deployment Plan |
24 Feb 2011 |
Amendment for Silt Curtain Deployment Plan |
11 May 2011 |
|
Condition 2.9 |
Silt Screen
Deployment Plan |
19 Oct 2010 |
Amendment for
Silt Screen Deployment Plan |
18 Feb 2011 |
|
Amendment for Silt Screen Deployment Plan |
15 Jun 2011 |
|
Condition 2.18 |
Proposal for
the Removal of Odorous Sediment and Slime |
13 Jan 2011 |
Amendment for Proposal for the Removal of
Odorous Sediment and Slime |
8 Mar 2011 |
|
Amendment for Proposal for the Removal of
Odorous Sediment and Slime |
2 Aug 2011 |
|
Condition 2.21 |
Landscape Plan |
18 Feb 2011 |
Condition 2.23 |
Noise Management Plan |
20 Oct 2010 |
|
Amendment for Noise Management Plan |
27 Jan 2011 |
3.1.9.
Implementation status of the recommended mitigation
measures during this reporting period is presented in Appendix 3.1.
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass over MTR Tsuen Wan Line
3.1.10.
Summary of the current status on licences and/or permits
on environmental protection pertinent and submission for contract no. HK/2010/06
under EP-356/2009 are shown in Table 3.10 and Table 3.11.
Table 3.10 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2010/06
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further
Environmental Permit |
FEP-05/356/2009 |
24 Mar 2011 |
N/A |
Valid |
FEP-08/364//2009/A |
15 June 2012 |
N/A |
Valid |
|
Notification of Works Under APCO |
326344 |
18 Jan 2011 |
N/A |
Valid |
Construction Noise Permit (CNP) for piling
equipment |
PP-RS0012-12 |
18 June 2012 |
6 Jul 2012 to
5 Jan 2013 |
Valid |
Construction Noise
Permit (CNP) for non-piling equipment |
GW-RS0989-12 |
21 Sept 2012 |
6 Oct 2012 to
5 Apr 2013 |
Granted |
|
GW-RS0313-12 |
27 Mar 2012 |
6 Apr to 5 Oct 2012 |
Valid |
GW-RS0658-12 |
21 June 2012 |
13 Jul 2012
to 12 Jan 2013 |
Valid |
|
Billing Account under Waste Disposal Ordinance |
7012338 |
16 Feb 2011 |
N/A |
Valid |
Registration as Chemical Waste Producer |
WPN5213-134-G2533-01 |
11 Feb 2011 |
N/A |
Valid |
Water Discharge
Licence |
WT00010905-2011 |
4 November 2011 |
31 July 2016 |
Valid |
Table 3.11 Summary
of submission status under EP-356/2009 and FEP-05/356/2009 Condition
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main Construction Companies |
24 October 2011 |
Condition 2.7 |
Works Schedule and Location Plans |
11 March 2011 |
Condition 2.8 |
Revised Silt Curtain Deployment Plan |
31 Aug 2011 |
Condition 2.9 |
Silt Screen Deployment Plan |
11 April 2011 |
Condition 2.23 |
Noise Management Plan |
11 March 2011 |
Contract no. HY/2009/19 ¡V Central- Wan Chai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
3.1.11.
Summary of the current status on licences and/or
permits on environmental protection pertinent for contract no. HY/2009/19 is
shown in Table 3.12.
Table 3.12 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/19
Permit / Licence / Notification /
Approval |
Reference No. |
Issued Date |
Valid Period / Expiry date |
Status |
Further Environmental Permit |
FEP-07/364/2009/A |
25 Feb 2011 |
Granted |
Valid |
Notification of Works Under APCO |
326160 |
24 Jan 2011 |
Notified |
Valid |
Construction Noise Permit (CNP) (For D-wall construction)
(Portion I, VII, VIII & IX) |
GW-RS0871-12 |
27-Aug-12 |
26-Feb-13 |
Valid |
Construction Noise Permit (CNP)
(For Bored pile construction at Portion III) |
GW-RS0507-12 |
22-May-12 |
23-Nov-12 |
Cancelled |
Construction Noise Permit (CNP)
(For Bored pile construction at Portion III, V) |
GW-RS0885-12 |
27-Aug-12 |
26-Feb-13 |
Valid |
Construction Noise Permit (CNP) (For |
GW-RS0589-12 |
18-Jun-12 |
17-Dec-12 |
Valid |
Construction Noise Permit (CNP)
(For IEC) |
GW-RS0953-12 |
17-Sep-12 |
20-Mar-13 |
Valid |
Discharge Licence (Land) |
WT00010093-2011 |
17 Aug 2012 |
30-Sept-16 |
Cancelled |
Discharge Licence (Sea) |
WT00010865-2011 |
03 Nov 2011 |
30-Nov-16 |
Valid |
Registration as a Waste Producer |
7012306 |
21 Jan 2011 |
Registered |
- |
C&D
Waste Disposal |
7012306 |
10 Feb 2011 |
Registered |
- |
Vessel
Disposal |
7013285 |
21 July 2011 |
Registered |
- |
Registration
as Chemical Waste Producer |
5213-151-C3654-01 |
24 Mar 2011 |
Registered |
- |
Dumping
Permit (Type 1 ¡V |
EP/MD/12-150 |
14-May-12 |
14-Nov-12 |
Valid |
Noise Monitoring Stations
4.1.1.
The noise monitoring stations for the Project are
listed and shown in Table 4.1 and Figure 4.1. Appendix 4.1 shows the
established Action/Limit Levels for the monitoring works.
Table 4.1 Noise Monitoring Station
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire
Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
Real-time Noise Monitoring
Stations
4.1.2.
The real-time noise monitoring stations for the
Project are listed and shown in Table 4.2 and Figure 4.1. Appendix 4.1 shows the
established Action/Limit Levels for the monitoring works.
Table 4.2 Real Time Noise Monitoring Station
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitefield Depot |
North Point |
RTN2 |
Oil Street Community Liaison Centre |
Noise Monitoring
Parameters, Frequency and Duration
4.1.3.
The construction noise level shall be
measured in terms of the A-weighted equivalent continuous sound pressure level
(Leq). Leq (30 minutes) shall be used as the monitoring
parameter for the time period between 0700 and 1900 hours on normal weekdays.
For all other time periods, Leq (5 minutes) shall be employed for
comparison with the Noise Control Ordinance (NCO) criteria. Supplementary
information for data auditing, statistical results such as L10 and L90 shall
also be obtained for reference.
4.1.4.
Noise monitoring shall be carried out at all the
designated monitoring stations. The monitoring frequency shall depend on the
scale of the construction activities. The following is an initial guide on the
regular monitoring frequency for each station on a weekly basis when noise
generating activities are underway:
¡P
one
set of measurements between 0700 and 1900 hours on normal weekdays.
4.1.5.
If construction works are extended to include works
during the hours of 1900 ¡V 0700 as well as public holidays and Sundays,
additional weekly impact monitoring shall be carried out during respective
restricted hours periods. Applicable permits under NCO shall be obtained by the
Contractor.
Monitoring Equipment
4.1.6.
As referred to in the Technical Memorandum ™ issued
under the NCO, sound level meters in compliance with the International
Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type
1) specifications shall be used for carrying out the noise monitoring. Immediately
prior to and following each noise measurement the accuracy of the sound level
meter shall be checked using an acoustic calibrator generating a known sound
pressure level at a known frequency. Measurements may be accepted as valid only
if the calibration level from before and after the noise measurement agree to
within 1.0 dB.
4.1.7.
Noise measurements shall not be made in fog, rain,
wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s.
The wind speed shall be checked with a portable wind speed meter capable of
measuring the wind speed in m/s.
Air Quality Monitoring
Stations
4.2.1.
The air monitoring stations for the Project are
listed and shown in Table 4.3 and Figure
4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.3 Air Monitoring
Station
Station ID |
Monitoring
Location |
Description |
CMA1b |
Oil Street Community
Liaison Centre |
North Point |
CMA2a |
|
|
CMA3a |
CWB PRE Site Office * |
|
CMA4a |
Society for the
Prevention of Cruelty to Animals |
Wan Chai |
CMA5a |
Children Playgrounds
opposite to |
Wan Chai |
CMA6a |
WDII PRE Site Office * |
Wan Chai |
* Remarks: As
per the ENPC meeting in January 2011, the monitoring stations CMA3a - Future
CWB site office at Wanchai Waterfront Promenade and CMA6a - Future AECOM site
office at Work Area were renamed as remark.
Air Monitoring Parameters,
Frequency and Duration
4.2.2.
One-hour and 24-hour TSP levels should be measured
to indicate the impacts of construction dust on air quality. The 24-hour TSP
levels shall be measured by following the standard high volume sampling method
as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part
50), Appendix B.
4.2.3.
All relevant data including temperature, pressure,
weather conditions, elapsed-time meter reading for the start and stop of the
sampler, identification and weight of the filter paper, and any other local
atmospheric factors affecting or affected by site conditions, etc., shall be
recorded down in detail.
4.2.4.
For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling Procedure and
Monitoring Equipment
4.2.5.
High volume samplers (HVSs) in compliance with the
following specifications shall be used for carrying out the 1-hour and 24-hour
TSP monitoring:
¡P
0.6
- 1.7 m3 per minute adjustable flow range;
¡P
equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
¡P
installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
¡P
capable
of providing a minimum exposed area of 406 cm2;
¡P
flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
¡P
equipped
with a shelter to protect the filter and sampler;
¡P
incorporated
with an electronic mass flow rate controller or other equivalent devices;
¡P
equipped
with a flow recorder for continuous monitoring;
¡P
provided
with a peaked roof inlet;
¡P
incorporated
with a manometer;
¡P
able
to hold and seal the filter paper to the sampler housing at horizontal
position;
¡P
easily
changeable filter; and
¡P
capable
of operating continuously for a 24-hour period.
4.2.6.
Initial calibration of dust monitoring equipment
shall be conducted upon installation and thereafter at bi-monthly intervals.
The transfer standard shall be traceable to the internationally recognized
primary standard and be calibrated annually. The concern parties such as IEC
shall properly document the calibration data for future reference. All the data
should be converted into standard temperature and pressure condition.
Laboratory Measurement /
Analysis
4.2.7.
A clean laboratory with constant temperature and
humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
4.2.8.
An alternative non-HOKLAS accredited
laboratory was set-up for carrying out the laboratory
analysis, the laboratory equipment was approved by the ER on 8 February 2011 and the measurement procedures were
witnessed by the IEC. Any measurement performed by the laboratory was
be demonstrated to the satisfaction of the ER and IEC. IEC shall regularly
audit to the measurement performed by the laboratory to ensure the accuracy of
measurement results.
4.2.9.
Filter paper of size 8" x 10" shall be
labelled before sampling. It shall be a clean filter paper with no pinholes,
and shall be conditioned in a humidity-controlled chamber for over 24-hours and
be pre-weighed before use for the sampling.
4.2.10.
After sampling, the filter paper loaded with dust
shall be kept in a clean and tightly sealed plastic bag. The filter paper shall
then be returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
readout down to 0.1 mg. The balance shall be regularly calibrated against a
traceable standard.
4.2.11.
All the collected samples shall be kept in a good
condition for 6 months before disposal.
impact monitoring for
odour patrol
4.2.12.
Odour patrols along the shorelines of Causeway Bay
Typhoon Shelter and ex-Wan Chai Public Cargo Working Area when there is
temporary reclamation in Causeway Bay Typhoon Shelter and/or in the ex-Wan Chai
Public Cargo Working Area, or when there is dredging of the odorous sediment
and slime at the south-western corner of the Causeway Bay Typhoon Shelter.
Odour patrols will be carried out at bi-weekly intervals during July, August
and September by a qualified person of the ET who shall:
¡P
be
at least 16 years of age;
¡P
be
free from any respiratory illnesses; and
¡P
not
be allowed to smoke, eat, drink (except water) or use chewing gum or sweets 30
min
¡P
before
and during odour patrol
4.2.13.
Odour patrol shall be conducted by independent
trained personnel / competent persons patrolling and sniffing around the shore
as shown in Figure
4.1 to detect any odour at the concerned hours (afternoon is
preferred for higher daily temperature).
4.2.14.
The qualified person will use the nose (olfactory
sensor) to sniff odours at different locations. The main odour emission sources
and the areas to be affected by the odour nuisance will be identified.
4.2.15.
The perceived odour intensity is to be divided into
5 levels which are ranked in the descending order as follows:
¡P
0 -
Not detected. No odour perceived or an odour so weak that it cannot be easily characterized
or described;
¡P
1 -
Slight Identifiable odour, and slight chance to have odour nuisance;
¡P
2 -
Moderate Identifiable odour, and moderate chance to have odour nuisance;
¡P
3 -
Strong Identifiable, likely to have odour nuisance;
¡P
4 -
Extreme Severe odour, and unacceptable odour level.
4.2.16.
The findings including odour intensity, odour
nature and possible odour sources, and also the local wind speed and direction
at each location will be recorded. In addition, some relevant meteorological
and tidal data such as daily average temperature, and daily average humidity,
on that surveyed day will be obtained from the Hong Kong Observatory Station
for reference. The Action and Limit levels for odour patrol are shown in Appendix 6.1.
4.2.17.
The qualified odour patrol member has individual
n-butanol thresholds complied with the requirement of European Standard Method
of Air Quality ¡V Determination of Odour Concentration by Dynamic Olfactometry
(EN13725) in the range of 20 to 80 ppb. The certificate for the qualified odour
panel member is shown in Appendix
4.2.
4.3.1.
The EIA Report has identified that the key water
quality impact would be associated with the dredging works during the
construction phase. Marine water quality monitoring for dissolved oxygen (DO),
suspended solid (SS) and turbidity is therefore recommended to be carried out
at selected WSD flushing water intakes. The impact monitoring should be carried
out during the proposed dredging works to ensure the compliance with the water
quality standards.
4.3.2.
The updated EM&A Manual for EP-356/2009
(Version in March 2011) is approval by EPD on 29 April 2011. As such, the
Action Level and Limit Level for the wet season (April ¡V September) will be
effected and applied to the water quality monitoring data from 30 April 2011.
Water Quality Monitoring Stations
4.3.3.
It is proposed to monitor the water quality at 9
WSD salt water intakes and 14 cooling water intakes along the seafront of the
Table 4.4 Marine Water Quality
Stations for Water Quality Monitoring
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD7 |
|
834150.0 |
818300.3 |
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
WSD10 |
Cha Kwo Ling |
841900.9 |
817700.1 |
WSD15 |
Sai Wan Ho |
841110.4 |
816450.1 |
WSD17 |
|
839790.3 |
817032.2 |
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
WSD20 |
|
830750.6 |
816030.3 |
WSD21 |
Wan Chai |
836220.8 |
815940.1 |
RW1 |
Wan Chai (Reprovision) |
836188.8 |
815911.1 |
Cooling Water Intake |
|||
C1 |
HKCEC Extension |
835885.6 |
816223.0 |
C2 |
Telecom House |
835647.9 |
815864.4 |
C3 |
HKCEC Phase I |
835836.2 |
815910.0 |
C4e |
Great Eagle Centre |
835932.8 |
815888.2 |
C4w |
Wan |
835629.8 |
815889.2 |
C5e |
Sun Hung Kai Centre (Eastern) |
836250.1 |
815932.2 |
C5w |
Sun Hung Kai Centre (Western) |
836248.1 |
815933.2 |
C6 |
Excelsior Hotel |
837009.6 |
815999.3 |
C7 |
|
837193.7 |
816150.0 |
C8 |
|
837970.6 |
816957.3 |
C9 |
Provident Garden |
838355.0 |
817116.6 |
RC1 |
Proposed HKAPA Extension |
835487.7 |
815987.7 |
RC5 |
Sun Hung Kai Centre (Reprovision) |
836291.4 |
816029.7 |
RC7 |
|
837245.2 |
816156.6 |
Water Quality Parameters
4.3.4.
Monitoring of dissolved oxygen (DO), turbidity and suspended
solids (SS) shall be carried out at WSD flushing water intakes and cooling
water intakes. DO and Turbidity are measured in-situ while SS is determined in
laboratory.
4.3.5.
In association with the water quality parameters,
other relevant data shall also be measured, such as monitoring
location/position, time, sampling depth, water temperature, pH, salinity,
dissolved oxygen (DO) saturation, weather conditions, sea conditions, tidal
stage, and any special phenomena and work underway at the construction site
etc.
Sampling Procedures and
Monitoring Equipment
4.3.6.
The interval between two sets of monitoring should
not be less than 36 hours except where there are exceedances of Action and/or
Limit Levels, in which case the monitoring frequency will be increased. Table
4.5 shows the proposed monitoring frequency and water quality
parameters. Duplicate in-situ measurements and water sampling should be carried
out in each sampling event. For selection of tides for in-situ measurement and
water sampling, tidal range of individual flood and ebb tides should be not
less than 0.5m.
Table 4.5 Marine Water Quality Monitoring Frequency and
Parameters
Activities |
Monitoring Frequency1 |
Parameters2 |
During the 4-week
baseline monitoring period |
Three days per week, at
mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
During marine construction works |
Three days per week, at
mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
After completion of marine construction works |
Three days per week, at
mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
Notes:
1.
For selection of tides for in-situ measurement
and water sampling, tidal range of individual flood and ebb tides should be not
less than 0.5m.
2.
Turbidity should be measured in situ whereas SS
should be determined by laboratory.
Dissolved Oxygen and
Temperature Measuring Equipment
4.3.7.
The instrument should be a portable, weatherproof
dissolved oxygen measuring instrument complete with cable, sensor,
comprehensive operation manuals, and use a DC power source. It should be
capable of measuring:
¡P
a
dissolved oxygen level in the range of 0-20 mg/l and 0-200% saturation
¡P
a
temperature of 0-45 degree Celsius
4.3.8.
It should have a membrane electrode with automatic
temperature compensation complete with a cable. Sufficient stocks of spare
electrodes and cables should be available for replacement where necessary.
(e.g. YSI model 59 meter, YSI 5739 probe, YSI 5795A submersible stirrer with
reel and cable or an approved similar instrument).
4.3.9.
Should salinity compensation not be build-in in the
DO equipment, in-situ salinity shall be measured to calibrate the DO equipment
prior to each DO measurement.
Turbidity Measurement
Instrument
4.3.10.
The instrument should be a portable, weatherproof
turbidity-measuring instrument complete with comprehensive operation manual.
The equipment should use a DC power source. It should have a photoelectric
sensor capable of measuring turbidity between 0‑1000 NTU and be complete with a
cable (e.g. Hach model 2100P or an approved similar instrument).
Sampler
4.3.11.
A water sampler comprises a transparent PVC
cylinder, with a capacity of not less than 2 litres, and can be effectively
sealed with latex cups at both ends. The sampler should have a positive
latching system to keep it open and prevent premature closure until released by
a messenger when the sampler is at the selected water depth (e.g. Kahlsico
Water Sampler or an approved similar instrument).
Sample Container and
Storage
4.3.12.
Water samples for suspended solids measurement
should be collected in high-density polythene bottles, packed in ice (cooled to
4¢XC without being frozen), and delivered to ALS Technichem (HK) Pty Ltd. as
soon as possible after collection for analysis.
Water Depth Detector
4.3.13.
A portable, battery-operated echo sounder shall be
used for the determination of water depth at each designated monitoring
station. This unit can either be handheld or affixed to the bottom of the
workboat, if the same vessel is to be used throughout the monitoring programme.
Salinity
4.3.14.
A portable salinometer capable of measuring
salinity in the range of 0-40 ppt shall be provided for measuring salinity of
the water at each of monitoring location.
Monitoring Position
Equipment
4.3.15.
A hand-held or boat-fixed type digital Global
Positioning System (GPS) with waypoint bearing indication or other equivalent
instrument of similar accuracy shall be provided and used during monitoring to
ensure the monitoring vessel is at the correct location before taking
measurements.
Calibration of In-situ
Instruments
4.3.16.
All in-situ monitoring instrument shall be checked,
calibrated and certified by a laboratory accredited under HOKLAS or equivalent
before use, and subsequently re-calibrated at 3 monthly intervals throughout
all stages of the water quality monitoring. Responses of sensors and electrodes
should be checked with certified standard solutions before each use. Wet bulb
calibration for a DO meter shall be carried out before measurement at each
monitoring location.
4.3.17.
For the on site calibration of field equipment by
the ET, the BS 127:1993, "Guide to Field and on-site test methods for the
analysis of waters" should be observed.
4.3.18.
Sufficient stocks of spare parts should be
maintained for replacements when necessary. Backup monitoring equipment shall
also be made available so that monitoring can proceed uninterrupted even when
some equipment is under maintenance, calibration, etc.
4.3.19.
Current calibration certificates of equipments are
presented in Appendix
4.2.
Laboratory Measurement /
Analysis
4.3.20.
Analysis of suspended solids has been carried out
in a HOKLAS accredited laboratory, ALS Technichem (HK) Pty Ltd. Water samples
of about 1L shall be collected at the monitoring stations for carrying out the
laboratory SS determination. The SS determination work shall start within 24
hours after collection of the water samples. The SS determination shall follow
APHA 19ed or equivalent methods subject to the approval of IEC and EPD.
Enhanced Water
Quality Monitoring in the ex-Wan Chai Public Cargo
Working Area
and the
4.3.21.
The enhanced water quality monitoring and audit
programme is to avoid aggravation of odour nuisance from seawater arising from
temporary reclamation in the ex-Wan Chai Public Cargo Working Area and the
Causeway Bay Typhoon Shelter.
4.3.22.
Dissolved oxygen monitoring at the intakes C6 and
C7 in Causeway Bay Typhoon Shelter when there is temporary reclamation in
Causeway Bay Typhoon Shelter and at the south-western and south-eastern corners
of the ex-Wan Chai Public Cargo Working Area. The proposed water quality
monitoring stations of the Project are shown in Table 4.6 and Figure 4.1.
Table 4.6 Marine
Water Quality Stations for Enhanced Water Quality Monitoring
Station |
Location |
C6 |
Excelsior Hotel |
C7 |
|
Ex-WPCWA-SW |
South-western of
the ex-Wan Chai Public Cargo Working Area |
Ex-WPCWA-SE |
South-eastern of
the ex-Wan Chai Public Cargo Working Area |
4.3.23.
The monitoring of dissolved oxygen are to be
carried out 3 days per week, at mid-flood and mid-ebb tides for 3 water depths
(1m below water surface, mid-depth and 1m above sea bed, except where the water
depth less than 6m, the mid-depth may be omitted. If the water depth be equal
to or less than 3m, only the mid-depth will be monitored).
Daily SS
Monitoring and 24 hours Turbidity Monitoring System
4.3.24.
During dredging of the sediment at the
south-western corner of the Causeway Bay Typhoon Shelter, daily monitoring of suspended
solids and 24 hour monitoring of turbidity at the cooling water intakes (C6 and
C7) shall be conducted.
4.3.25.
The 24 hours monitoring of turbidty at the cooling water
intakes (C6 and C7) shall be established by setting up a continuous water quality
monitoring station in front of the intakes during the dredging activities. The
monitoring system include the turbidity sensor and data logger which is capable of data capturing at
every 5 minutes. The data sahll be downloaded daily and compared with the
Action and Limit level determined during the baseline water qualtiy monitoring
at the cooling water intake locations.
Additional Dissovled
oxygen Monitoring FOR CULVERT L WATER DISCHARGE FLOW
4.3.26.
In
response to the Condition 2.18 of the Environmental Permit no. EP-356/2009
requiring that a silt curtain / impermeable barrier system be installed to
channel water discharge flow from Culvert L to locations outside the embayment
area, a proposed replacement of the requirement with additional dissolved
oxygen monitoring has been conducted at three monitoring stations, namely A, B
and C between the eastern seawall of Central Reclamation Phase III and the
HKCEC Extension since November 2011 under EP-356/2009 so that DO level between
the eastern seawall of Central Reclamation Phase II and the HKCEC extension
could be continuously monitored.
4.3.27.
The proposed DO monitoring stations of the Project
are shown in Table 4.7 and Figure
4.1.
Table 4.7 Marine
Water Quality Stations for Additional DO Monitoring
Station |
Easting |
Northing |
A |
835468 |
815857 |
B |
835572 |
815961 |
C |
835659 |
816271 |
4.3.28.
The monitoring of dissolved oxygen are to be
carried out once per week, at mid-flood and mid-ebb tides for 3 water depths
(1m below water surface, mid-depth and 1m above sea bed, except where the water
depth less than 6m, the mid-depth may be omitted. If the water depth be equal to
or less than 3m, only the mid-depth will be monitored).
5.0.1.
The environmental monitoring will be implemented
based on the division of works areas of each designed project managed under
different contracts with separate FEP applied by individual contractors.
Overall layout showing work areas of various contracts, latest status of work
commencement and monitoring stations is shown in Figure
2.1 and Figure
4.1. The
monitoring results are presented in according to the Individual Contract(s).
5.0.2.
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The
construction site was handed over to contractor HY/2009/19 on 31 December 2011.
5.0.3.
The surrender of the Further Environmental Permit
for HY/2009/11 withdrew by contractor on 14 February 2012. However, there is no
work was conducted by the contractor.
5.0.4.
In the reporting month, the concurrent contracts
are as follows:
Contract no. HY/2009/11 Central - Wan Chai Bypass - North Point
Reclamation;
Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central-Wan
Chai Bypass at
Contract no. HK/2009/02 Wan Chai Development Phase II ¡V Central-Wan Chai
Bypass at Wan Chai East
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
Contract no. HK/2010/06 Wan Chai Development Phase II ¡V Central-Wan Chai
Bypass over MTR Tsuen Wan Line
Contract no. HY/2009/19- Cental- Wan Chai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link
5.0.5.
The environment monitoring schedules for reporting
month and coming month are presented in Appendix 5.1.
Contract no. HY/2009/11 ¡V Central ¡V
Wanchai Bypass, North Point Reclamation
5.1.1.
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The
construction site was handed over to contractor HY/2009/19 on 31 December 2011
and the FEP-01/356/2009 was under application of surrender in this reporting
period. The monitoring was temporary suspended since 5 January 2012.
5.1.2.
The proposed division of noise monitoring stations
for Contract no. HY/2009/11 are summarized in Table 5.1 below:
Table 5.1 Noise
Monitoring Stations for Contract no. HY/2009/11
Station |
Description |
M4b |
Victoria Centre |
M5b |
|
5.1.3.
Day time and evening period noise monitoring was
conducted at the
5.1.4.
Noise monitoring results measured in this reporting
period are reviewed and summarized. No exceedance was recorded in reporting
month. Details of noise monitoring results and graphical presentation can be
referred in Appendix 5.2.
Contract no. HK/2009/01 - Wan Chai
Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC, Contract no.
HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
WanChai East and Contract no. HK/2010/06 Wan Chai Development Phase II ¡V
Central-Wan Chai Bypass over MTR Tsuen Wan Line
5.1.5.
The proposed division of noise monitoring stations
are summarized in Table 5.2 below.
Table 5.2 Noise
Monitoring Station for Contract nos. HK/2009/01, HK/2009/02 and HK/2010/06
Station |
Description |
M1a |
Harbour Road Sports Centre |
5.1.6.
Daytime and evening period noise monitoring was
conducted at the Harbour Road Sport Centre in the reporting month.
5.1.7.
No exceedance was recorded in this reporting
period. Details of noise monitoring results and graphical presentation can be
referred in Appendix 5.2
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
5.1.8.
The noise monitoring for HY/2009/15 was commenced
on 10 November 2010. The proposed division of noise monitoring stations are
summarized in Table 5.3 below.
Table 5.3 Noise
Monitoring Station for Contract no. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
5.1.9.
Noise monitoring results measured in the period of
daytime and restricted hour are reviewed and summarized. No exceedance was
recorded in this reporting period. Details of noise monitoring results and
graphical presentation can be referred in
Appendix 5.2
Contract no. HY/2009/19- Wan Chai
Bypass Tunnal (North Point Section) and Island Eastern Corridor Link
5.1.10.
The proposed division of noise monitoring stations
are summarized in Table 5.4 below.
Table 5.4 Noise
Monitoring Station for Contract no. HY/2009/19
Station |
Description |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
5.1.11.
Three limit level exceedances were recorded at M6
on 4,20 and 27 September 2012 in this reporting month. Details of noise monitoring results and graphical
presentation can be referred in Appendix 5.2
Contract no.
HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point Reclamation and Contract no.
HY/2009/19 ¡V Central- Wan Chai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link
5.2.1.
Oil Street Community Liaison Centre was confirmed
to be demolished in mid-October by CWB RSS. This presented a need for relocation of
RTN2 ¡V Oil Street Community Liaison Centre. After liaison with Hong Kong Electric,
permission was granted on 21 Sep 2012 for real time noise monitoring set up at
City Garden Electric Centre (RTN2a ¡V Electric Centre), which is a representative of the noise sensitive
receiver City Garden. The tentative
schedule for relocation of RTN2 is on 5 Oct 2012.
5.2.2.
The major work activities for Contract no. HY/2009/11
was confirmed substantial complete by RSS on 4 January 2012. The construction
site was handed over to contractor HY/2009/19 on 31 December 2011 and the FEP-01/356/2009
was under application of surrender in this reporting period.
5.2.3.
Real-time noise monitoring at FEHD Hong Kong
Transport Section Whitefield Depot commenced external wall renovation since 1
June 2012
Table 5.5 Real
Time Noise Monitoring Station for Contract no. HY/2009/11 and HY/2009/19
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD
Hong Kong Transport Section
Whitefield Depot |
North Point |
RTN2 |
Oil
Street Community Liaison
Centre |
* Real time noise
monitoring results and graphical presentation during night time period are for
information only.
5.2.4.
Details of real time noise monitoring results and
graphical presentation can be referred to Appendix
5.5.
5.3.1.
Due to extension of site boundary by contractor of
HY/2009/19, location of air monitoring station CMA1b ¡V Oil Street Community
Liaison Centre has been finely adjusted on 21 April 2012.
5.3.2.
Due to lack of electricity supply, the 24-hr TSP
monitoring at the following stations were rescheduled:
CMA1b: from 6 and 24 September 2012 to 7 and
25 September 2012
CMA3a: from 18 September 2012 to 19 September
2012
CMA4a: from 24 September 2012 to 25 September
2012
CMA5a: from 31 August and 24 September 2012
to 1 and 26 September 2012
CMA6a: from 31 August 2012 to 1 September
2012
Contract no. HY/2009/11 ¡V Central ¡V
Wanchai Bypass, North Point Reclamation
5.3.3.
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The
construction site was handed over to contractor HY/2009/19 on 31 December
2011and the FEP-01/356/2009 was valid in this reporting period. The monitoring
for the contract was temporary suspended on 6 January 2012.
5.3.4.
The proposed division air monitoring stations is
summarized in Table 5.6 below.
Table 5.6 Air
Monitoring Stations for Contract no. HY/2009/11
Station |
Description |
CMA1b |
Oil Street Community Liaison Centre |
CMA2a |
|
5.3.5.
No exceedance was recorded in the reporting month.
Details of air monitoring results and graphical presentation can be referred in
Appendix
5.3.
Contract no. HK/2009/01 - Wan Chai
Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC
5.3.6.
Air monitoring was commenced on 1 April 2011 in
response to the commencement of the land-filling work for Contract no.
HK/2009/01. The proposed divisions of air monitoring stations are summarized in
Table 5.7 below. No exceedance was recorded in the reporting
month.
Table 5.7 Air
Monitoring Stations for Contract no. HK/2009/01
Station |
Description |
CMA5a |
Children Playgrounds opposite to |
CMA6a |
WDII PRE Site Office |
Contract no. HK/2009/02 - Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
5.3.7.
Air monitoring was commenced in mid-January 2011
for the land-filling work for Contract no. HK/2009/02. The proposed division of
air monitoring stations are summarized in Table 5.8 below. No
exceedance was recorded in the reporting month.
Table 5.8 Air
Monitoring Station for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
Contract
no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
5.3.8.
Air monitoring was commenced on 15 March 2011 for
the land filling work for Contract no. HY/2009/15. The proposed division of air
monitoring stations are summarized in Table 5.9 below. No
exceedance was recorded in the reporting month.
Table 5.9 Air
Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB PRE Site Office |
5.3.9.
The odour patrol along the odour route with 7
sniffing locations was conducted by a qualified odour patrol member on 3 and 17
September 2012 at the concerned hours (afternoon for higher daily temperature).
No exceedance was recorded in this reporting month. The details of the odour
patrol results and meteorological conditions and on the date of odour patrol
are shown in Appendix 5.3.
Contract
no. HY/2009/19- Wan Chai Bypass Tunnal (North Point Section) and Island Eastern
Corridor Link
5.3.10.
The proposed division of air monitoring stations
are summarized in Table 5.10 below. No exceedance was recorded in the reporting
month.
Table
5.10 Air Monitoring Stations for Contract
no. HY/2009/19
Station |
Description |
CMA1b |
Oil St Community
Liaison Centre |
CMA2a |
|
5.4.1.
Due
to the enforcement of Amber Rainstorm on 24 September 2012, water quality
monitoring at flood tide was cancelled.
5.4.2.
Based
on the safety concern of the malfunctioned lightning system for the access to
C5e and C5w water quality monitoring stations on 22 September 2012, the water
quality monitoring stations at C5e and C5w were temporary suspended on 22
September 2012 at ebb tide.
5.4.3.
WDII/RSS
advised that the dredging works for submarine pipeline at
5.4.4.
Based
on the joint inspection on 4 Jan 2012 for the NPR area, the 4-week water quality
monitoring at WSD9, WSD10, WSD15, WSD17, C8, C9 to confirm no water
deterioration with respect to NPR was commenced since 7 Jan 2012 and it was
completed on 6 February 2012.
5.4.5.
Water
quality monitoring at WSD10 and WSD15 was temporary suspended while water
quality monitoring at WSD9 and WSD17 was implemented with respect to HK/2009/02
from 8 Feb 12 onwards;
5.4.6.
Water
quality monitoring at C8 and C9 have been implemented with respect to
HY/2009/19 since the marine bore piling work started on 28 Jan 12.
5.4.7.
Based
on the safety concern when external façade refurbishment was conducted by
contractor employed by Provident Centre (C9) since 3 Feb 2012, there is a fine
adjustment of the sampling location of water quality monitoring at C9 to the
closest accessible point prior to the completion of the external façade
refurbishment work.
5.4.8.
With respect to the trial
dredging at WCR2 was scheduled on 20, 22, 24, 25 March and 1, 3 ,
11, 13, 15, 17, 19, 20 Apr and
3 May 2012, on-going water quality monitoring results at WSD21 during
this period was checked and indicated that there was no contribution due to the
trial dredging operation. Enhanced review of water quality around WCR2
was also implemented and no deterioration in the water quality was observed.
5.4.9.
Due to the access of water
monitoring station at WSD19 was blocked by LCSD construction works from 3 April
2012 to 2 May 2012 and lead to the inaccessibility of sampling either land and
marine, there is a fine adjustment of the sampling point of WSD 19 since 5
April 2012 to the closest accessible point prior to the completion of the
construction activities.
5.4.10.
Due to the dredging works for
Cross Harbour Water Mains from Wan Chai to Tsim Sha Tsui- DP6 was completed on
26 March 2012, the temporary suspension of impact water quality monitoring at
WSD7 and WSD20 after 27 April 2012 for the water quality monitoring at WSD7 and
WSD20 have been monitored for 4-week period after the completion of DP6 to
confirm no water deterioration.
Contract no. HY/2009/11 ¡V Central ¡V
Wanchai Bypass, North Point Reclamation
5.4.11.
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The
construction site was handed over to contractor HY/2009/19 on 31 December 2011
and the FEP-01/356/2009 was valid in this reporting period.
5.4.12.
The proposed division of water monitoring stations
for Contract no. HY/2009/11 are summarized in Table 5.11 below:
Table 5.11 Water Monitoring Stations for Contract no. HY/2009/11
Station
Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
WSD10 |
Cha Kwo Ling |
841900.9 |
817700.1 |
WSD15 |
Sai Wan Ho |
841110.4 |
816450.1 |
WSD17 |
|
839790.3 |
817032.2 |
Cooling Water Intake |
|||
C8 |
|
837970.6 |
816957.3 |
C9 |
Provident Garden |
838355.0 |
817116.6 |
Remarks:
WSD9, WSD10, WSD15, WSD17, C8 and C9 water monitoring finished on 6 Feb 2012.
Contract no. HK/2009/01 - Wan Chai
Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC
5.4.13.
Water monitoring for Contract no. HK/2009/01 was
commenced on 23 July 2010. The proposed division of water monitoring stations
are summarized in Table 5.12 below.
Table 5.12 Water Monitoring Stations for Contract no. HK/2009/01
Station
Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD7 |
|
834150.0 |
818300.3 |
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
WSD20 |
|
830750.6 |
816030.3 |
Cooling Water Intake |
|||
C1 |
HKCEC
Extension |
835885.6 |
816223.0 |
C2 |
Telecom
House |
835647.9 |
815864.4 |
C3 |
HKCEC Phase
I |
835836.2 |
815910.0 |
C4e |
Great Eagle
Centre |
835932.8 |
815888.2 |
C4w |
Wan |
835629.8 |
815889.2 |
Remarks:
- The
water monitoring stations for the dredging works under Contract No. HK/2009/01
should also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at
these locations have not been carried out by others. Similarly, the water
monitoring stations for the dredging works under Contract No. HK/2009/02 should
also include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality
monitoring at these locations have not been carried out by others.
- WSD7 and WSD20 water
quality monitoring were temporarily suspended since 27 Apr 2012.
Contract no. HK/2009/02 - Wan Chai
Development Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
WanChai East
5.4.14.
Water monitoring for Contract no. HK/2009/02 was
commenced on 8 July 2010. The proposed division of water monitoring stations
are summarized in Table 5.13 below.
Table 5.13 Water Monitoring Stations for Contract no. HK/2009/02
Station
Ref. |
Location |
Easting |
Northing |
|||
WSD Salt Water Intake |
||||||
WSD21 |
Wan Chai |
836220.8 |
815940.1 |
|||
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
|||
WSD17 |
|
839790.3 |
817032.2 |
|||
Cooling Water Intake |
||||||
C5e |
Sun Hung Kai
Centre (Eastern) |
836250.1 |
815932.2 |
|||
C5w |
Sun Hung Kai
Centre (Western) |
836248.1 |
815933.2 |
|||
Remarks:
-
The
water monitoring stations for the dredging works under Contract No. HK/2009/01
should also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at
these locations have not been carried out by others. Similarly, the water
monitoring stations for the dredging works under Contract No. HK/2009/02 should
also include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality
monitoring at these locations has not been carried out by others.
-
Water
quality monitoring at WSD9 and WSD 17 was implemented with respect to
HK/2009/02 from 8 Feb 2012.
Contract no. HK/2010/06
- Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass over MTR Tsuen Wan
Line
5.4.15.
Water monitoring for Contract no. HK/2010/06 was
commenced on 8 March 2011. The proposed division of water monitoring stations
are summarized in Table 5.14 below.
Table 5.14 Water Monitoring Stations for Contract no. HK/2010/06
Station
Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C2 |
Telecom
House |
835647.9 |
815864.4 |
Contract
no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
5.4.16.
As
the removal of reclamation work of TS1 at CBTS has been completed, all
procedures have been rectified and complied with the conditions set in
EP-356/2009 and FEP-04/356/2009.
5.4.17.
Due to the commencement of the maintenance dredging
on 10 November 2010, water quality monitoring for Contract no. HY/2009/15 was
commenced on 9 November 2010. The proposed division of water monitoring
stations are summarized in Table 5.15 below.
Table 5.15 Water Monitoring Stations for
Contract no. HY/2009/15
Station
Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C6 |
Excelsior Hotel |
837009.6 |
815999.3 |
C7 |
|
837193.7 |
816150.0 |
Remarks: - The cessation of seawater intake
operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was
then terminated since 17 May 2011.
Contract no. HY/2009/19 ¡V Central- Wan
Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
5.4.18.
Due to the commencement of the marine bored piling
on 28 Jan 2012, water quality monitoring for Contract no. HY/2009/19 was
commenced on 28 Jan 2012. The proposed division of water monitoring stations
are summarized in Table 5.16 below.
Table 5.16 Water Monitoring Stations for Contract no. HY/2009/19
Station
Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C8 |
|
837970.6 |
816957.3 |
C9 |
Provident Garden |
838355.0 |
817116.6 |
Remarks: C8 and C9 monitoring commenced on 28 Jan 2012.
5.4.19. Based on the safety concern when
external façade refurbishment was conducted by contractor employed by Provident
Center (C9) between 9 January 2012 to 30 July 2012 which caused to the
inaccessibility of sampling either land and marine since 3 Feb 2012, there is a
fine adjustment of the sampling location of water quality monitoring at C9
since 10 March 2012 to the closest accessible point prior to the completion of
the external façade refurbishment work.
5.4.20. Due to the access of water monitoring
station at WSD19 was blocked by LCSD construction works from 3 April 2012 to 2
May 2012 and lead to the inaccessibility of sampling either land and marine,
there is a fine adjustment of the sampling point of WSD 19 since 5 April 2012
to the closest accessible point prior to the completion of the construction
activities.
5.4.21. As per the meeting with the
representative of Excelsior Hotel and World Trade Centre on 17 May 2011, they
confirmed that the seawater intake for The Excelsior was no longer in use and
replaced by the connected permanent water supply from WSD pipelines since 11
January 2011. Thus, the impact water quality monitoring for the cooling intake
- C6 was terminated effective from 26 May 2011.
5.4.22. 24 hours monitoring of turbidity at the cooling water intakes at
C7 was conducted. With respect to the seawall collapsing
at TS4 on 17 November 2011, the 24 hours turbidity monitoring and was kept in
November 2011. Since the reinstating
the seawall was completed on 13 January 2012 and no any water deterioration was
performed, 24 hour turbidity monitoring was then suspended on 27 January 2012.
5.4.23.
Water monitoring results measured in this reporting
period are reviewed and summarized. Details of water quality monitoring results and
graphical presentation can be referred in Appendix 5.4.
Table 5.17 Summary
of Water Quality Monitoring Exceedances in Reporting Month
Contract no. |
Water Monitoring Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
|||||||||
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|||
HY/2009/11 |
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Monitoring finished
on 6 Feb 2012 |
WSD10 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD15 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C8 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/01 |
WSD19 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C3 |
1 |
0 |
0 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
0 |
0 |
|
|
C4e |
0 |
0 |
0 |
0 |
0 |
0 |
3 |
0 |
0 |
0 |
0 |
0 |
|
|
C4w |
1 |
0 |
0 |
0 |
0 |
0 |
3 |
0 |
0 |
0 |
0 |
0 |
|
Monitoring finished
on 27 April 2012 |
WSD20 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
HK/2009/01 & HK/2010/06 |
C2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/02 |
C5e |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
|
|
C5w |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Monitoring started
on 8 Feb 2012 |
WSD21 |
1 |
0 |
0 |
0 |
0 |
0 |
2 |
2 |
0 |
0 |
0 |
0 |
|
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
||
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HY/2009/15 |
C7 |
1 |
1 |
0 |
0 |
0 |
0 |
3 |
0 |
0 |
0 |
0 |
0 |
|
HY/2009/19 Monitoring started on 28 Jan 2012 |
C8 |
0 |
0 |
1 |
0 |
1 |
0 |
1 |
0 |
0 |
1 |
0 |
0 |
|
C9 |
1 |
0 |
0 |
2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
Total |
6 |
1 |
1 |
2 |
1 |
0 |
14 |
3 |
0 |
1 |
0 |
1 |
||
Remarks:
- The cessation of seawater intake operation for
C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated
since 17 May 2011.
-
WSD9 and WSD17 were implemented with respect to HK/2009/02 from 8 Feb 2012.
-
4-week water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8, C9
were completed on 6 Feb 2012.
- C8 and C9 were
implemented with respect to HY/2009/19 from 28 Jan 2012.
- WSD7 and WSD20 were
temporarily suspended from 27 Apr 2012
5.4.24. Enhanced DO monitoring at 4 monitoring
stations in Causeway Bay Typhoon Shelter and Ex-Public Cargo Works Area was
conducted three days per week during the reporting period. The action and limit
level exceedances of water quality monitoring are summarized in Table 5.18.
Table 5.18 Summary of Enhanced Dissolved Oxygen Monitoring
Exceedances in Reporting Month
Contract
no. |
Water
Monitoring Station |
Mid-flood |
Mid-ebb |
||
DO |
DO |
||||
|
LL |
|
LL |
||
HY/2009/15 |
C6 |
0 |
0 |
1 |
0 |
C7 |
1 |
1 |
2 |
1 |
|
Ex-WPCWA SW |
2 |
4 |
0 |
7 |
|
Ex-WPCWA SE |
4 |
4 |
2 |
8 |
|
Total |
7 |
9 |
5 |
16 |
5.4.25.
There were 12 action level exceedances and 25 limit
level exceedances recorded in enhanced dissolved oxygen monitoring in this
reporting period.
5.4.26. In response to the Condition 2.18 of
the Environmental Permit no. EP-356/2009 requiring that a silt curtain /
impermeable barrier system be installed to channel water discharge flow from
Culvert L to locations outside the embayment area, a proposed replacement of
the requirement with additional dissolved oxygen monitoring has been conducted
at three monitoring stations, namely A, B and C between the eastern seawall of
Central Reclamation Phase III and the HKCEC Extension since November 2011 under
EP-356/2009 so that DO level between the eastern seawall of Central Reclamation
Phase II and the HKCEC extension could be continuously monitored. Details of additional DO monitoring results can be
referred in Appendix 5.4a.
Contract no. HY/2009/11 ¡V Central ¡V
Wanchai Bypass, North Point Reclamation
5.5.1.
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012.
Therefore, no C&D waste was generated.
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
5.5.2.
Inert C&D waste was recycled and non- inert
C&D waste was disposed of in this reporting month. Details of the waste
flow table are summarized in Table 5.19.
Table 5.19 Details
of Waste Disposal for Contract no. HK/2009/01
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
0 |
22245.415 |
TKO137, TM38 |
Inert C&D materials recycled, m3 |
20 |
4999.5 |
N/A |
Non-inert C&D materials disposed, m3 |
74.06 |
1016.94 |
|
Non-inert C&D materials recycled, kg |
0 |
151143 |
N/A |
Chemical waste disposed, kg |
600 |
7800 |
N/A |
*Marine Sediment (Type 1 ¡V Open Sea Disposal), m3 |
0 (Bulk Volume) |
91164.2 (Bulk Volume) |
South of Cheung Chau |
* Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites)
& Type 2 ¡V Confined Marine Disposal) , m3 |
0 (Bulk Volume) |
43018 (Bulk Volume) |
East of Cha Chau |
Dredged Sediment Requiring Type 3
¡V Special Treatment / Disposal contained in Geosynthetic Containers |
0 (Bulk Volume) |
5613 (Bulk Volume) |
East of Cha Chau |
5.5.3.
There were no marine sediments Type 1 ¡V Open Sea Disposal (Dedicate
Sites) & Type 2 ¡V Confined Marine Disposal disposed in the reporting month.
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
5.5.4.
Inert and non- inert C&D waste were disposed of
in this reporting month. Details of the waste flow table are summarized in Table
5.20.
Table 5.20 Details
of Waste Disposal for Contract no. HK/2009/02
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
26,509 |
200,807 |
TKO137 / TM 38 |
Inert C&D materials recycled, m3 |
NIL |
18161 |
N/A |
Non-inert C&D materials disposed, m3 |
23 |
609 |
SENT Landfill |
Non-inert C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Chemical waste disposed, kg |
800 |
5521 |
N/A |
Marine Sediment (Type 1 ¡V Open Sea Disposal), m3 |
NIL |
154,827 (Bulk volume) |
South of Cheung Chau |
Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites)
& Type 2 ¡V Confined Marine Disposal) , m3 |
Nil |
114464 (Bulk volume) |
East of Sha Chau |
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V
Tunnel (
5.5.5.
Marine sediment (Type 1 ¡V Open Sea Disposal) was disposed of in
this reporting month. Details of the waste flow table are summarized in Table
5.21
Table 5.21 Details
of Waste Disposal for Contract no. HY/2009/15
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
NIL |
141579.2 |
Tuen Mun Area 38 |
NIL |
65216 |
TKO137 FB |
|
Inert C&D materials recycled, m3 |
NIL |
184.0 |
To Contract HY/2009/11 |
NIL |
304 |
ex-PCWA |
|
NIL |
111.9 |
TS4 |
|
Non-inert C&D materials disposed, m3 |
NIL |
252.2 |
SENT Landfill |
Non-inert C&D materials recycled, kg |
NIL |
299361.5 |
N/A |
Chemical waste disposed, kg |
NIL |
8,200 |
N/A |
Marine Sediment (Type 1 ¡V Open Sea Disposal),
m3 |
980 |
97,857 (Bulk Volume) |
South of Cheung Chau |
Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) &
Type 2 ¡V Confined Marine Disposal) , m3 |
NIL |
207,285 (Bulk Volume) |
East of Sha Chau |
Marine
Sediment (Type 3 ¡V Special Treatment / Disposal contained in Geosynthetic
Containers) |
NIL |
7,050 (Bulk Volume) |
East of Sha Chau |
There was marine sediment Type 1- Open Sea Disposal
disposed of in the reporting month.
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line
5.5.6.
Non-inert C&D waste was recycled of in this
reporting month. Details of the waste flow table are summarized in Table
5.22.
Table 5.22 Details
of Waste Disposal for Contract no. HK/2010/06
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
338.4 |
11366.23 |
TM38 |
Inert C&D materials recycled, m3 |
NIL |
266.8 |
N/A |
Non-inert C&D materials disposed, m3 |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled, kg |
0 |
1374.5 |
N/A |
Chemical waste disposed, L |
0 |
600 |
N/A |
Marine Sediment (Type 1 ¡V Open Sea Disposal), m3 |
0 (Bulk Volume) |
3,694 (Bulk Volume) |
South Cheung Chau |
Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) &
Type 2 ¡V Confined Marine Disposal) , m3 |
0 (Bulk Volume) |
12,297 (Bulk Volume) |
|
There were no marine
sediments Type
1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal dredging from
bore-piling casing in the reporting month.
Contract no. HY/2009/19 ¡VCentral- WanChai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
5.5.7.
Inert and non-inert C&D waste were disposed of
in this reporting month. Details of the waste flow table are summarized in Table
5.23.
Table 5.23 Details of Waste Disposal for
Contract no. HY/2009/19
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
18999.07 |
55584.77 |
TM38 |
Inert C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed, m3 |
28.85 |
84.82 |
N/A |
Non-inert C&D materials recycled, kg |
NIL |
NIL |
N/A |
Chemical waste disposed, L |
NIL |
0.29 |
N/A |
Marine Sediment (Type 1 ¡V Open Sea Disposal), m3 |
83 |
83 |
South Cheung Chau |
Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) &
Type 2 ¡V Confined Marine Disposal) , m3 |
377 |
482 |
|
There were
marine sediments Type1- Open Sea Disposal and Type
1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal dredging from bore-piling casing in the reporting
month.
6.0.1.
The Event Action Plan for construction noise, air
quality and water quality are presented in Appendix 6.1.
Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point
Reclamation
6.1.1
No exceedance was recorded in the reporting month.
Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central
¡VWanchai Bypass at HKCEC
6.1.2
No exceedance was recorded in the reporting month.
Contract no.
HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
WanChai East
6.1.3
No exceedance was recorded in the reporting month.
Contract no.
HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
6.1.4
No exceedance was recorded in the reporting month.
Contract no.
HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass over MTR
Tsuen Wan Line
6.1.5
No exceedance was recorded in the reporting month.
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
6.1.6
Three limit level exceedances were recorded at M6 ¡V HK
Baptist Church Henrietta Secondary School on 4, 20 and 27 September 2012 in the
reporting month.
Investigations found that major
traffic noise was contributed in the noise monitoring and not related to the Project.
6.2.1
No exceedance was recorded in the reporting month.
6.3.1.
No exceedance was recorded in 1-hr TSP and 24-hrs
TSP monitoring in the reporting month.
6.3.2.
No exceedance for odour patrol monitoring was
recorded in the reporting month.
Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point
Reclamation
6.4.1
No exceedance was recorded in the reporting month.
Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central
¡VWanchai Bypass at HKCEC
6.4.2
There were occasionally DO exceedances recorded at C3,
C4e and C4w in this reporting month. No odour nuisance was noted during DO monitoring.
Confirmed with Contractor, there was no work conducted during the water quality
monitoring. The exceedances were possible in relation to the natural variation
or changes of water quality in the vicinity of the water quality monitoring
station.
6.4.3
DO exceedances at C3 were recorded on 12 September
2012. Confirmed with Contractor, there was no work conducted on that day. After
checking with Contractor, floating debris was observed within silt screen and
the debris was removed after inspection. The exceedances were possible in
relation to the accumulation of floating debris in the vicinity of the
monitoring station.
6.4.4
DO exceedances at C3 were recorded on 3 September
2012. Confirmed with Contractor, there was no work conducted on that day. The
exceedance was possible in relation to the accumulation of floating debris near
to the intake. Contractor was reminded the water quality near to the intake
should be provided with sufficient inspection and prevents the accumulation of
floating rubbish. The exceedance was considered not project related.
Contract no.
HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
WanChai East
6.4.5
There was one DO exceedance at mid-flood recorded
at WSD21 on 3 September 2012. No odour nuisance was noted during DO monitoring.
Checking with Contractor¡¦s work, rockfilling in WCR2 was conducted on that day.
Checking with contractor's inspection record, the silt screen and silt curtain
for rockfilling were in proper condition on that day. The exceedance was
considered as natural variation or changes of water quality in the vicinity of
the water quality monitoring station and not project related.
6.4.6
There was SS exceedance at mid-ebb recorded at C5e on
19 September 2012. Confirmed with Contractor, there was no work conducted on that
day. The exceedance was possibly due to cleaning of
screen panels at the pumping station. Materials from the cleaning of screen
panels were unavoidably collected during monitoring. The exceedance was
considered as not project related.
6.4.7
There was DO exceedance at mid-flood recorded at C5e
on 12 September 2012 in this reporting month. No odour nuisance was noted
during DO monitoring. Confirmed with Contractor, there was no work conducted
during the water quality monitoring. The exceedance was considered as natural
variation or changes of water quality in the vicinity of the water quality
monitoring station and not project related.
6.4.8
There were occasionally DO exceedances recorded at WSD21
and WSD9 in this reporting month. No odour nuisance was noted during DO monitoring.
Confirmed with Contractor, there was no work conducted during the water quality
monitoring. The exceedances were possible in relation to the low flow and low
water depth during ebb tide and considered as not project related.
Contract no.
HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
6.4.9
There were occasionally DO exceedances recorded at
C7 in this reporting month. After checking with the Contractor¡¦s works, the
deployed silt curtain was in proper condition for TS2 seawall construction. The
exceedances were possible in relation to the accumulation of particles
discharged from outfalls near monitoring station. The exceedances were
considered not related to Project works.
6.4.10 There was one DO
action level exceedance at C6 on 14 September 2012. No odour nuisance was noted
during the DO monitoring. Checked with Contractor's works, TS2 seawall
construction was conducted on that day. Reviewing the results at the monitoring
stations nearer than C6, no exceedance was recorded. The exceedance was
possible in relation to the low flow and low water depth during ebb tide and
considered not related to Project works.
6.4.11 There were
occasionally DO exceedances at Ex-WPCWA SE and Ex-WPCWA SW recorded in this
reporting month. No odour nuisance was noted during DO monitoring. After
checking with Contractor, there was no marine work undertaken at ex-WPCWA. The
exceedances were possible in relation to the accumulation of organic particles
discharge from culvert near monitoring station and considered not related to the Projects works.
Contract no.
HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass over MTR
Tsuen Wan Line
6.4.12 No exceedance
was recorded in this reporting month.
Contract no.
HY/2009/19- Central- Wan Chai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link
6.4.13 There were
occasionally DO and turbidity exceedances at C8 and C9 recorded in this
reporting month. Confirmed with Contractor, there was no marine work conducted
near C8 and C9.The exceedances were possible in relation to the accumulation of
particles discharged from outfalls near monitoring stations and not related to
project.
6.4.14 Summary for
notification of exceedances can be referred to Appendix 6.2.
6.5.1
There was no non-compliance from the site audits in
the reporting month. The observations and recommendations made in each
individual site audit session were presented in Section 8.
6.6.1
There was no particular action taken since no
project-related non-compliance was recorded from the site audits and
environmental monitoring in the reporting month.
7.0.1.
According to Condition 3.4 of the EP-356/2009, this
section addresses the relevant cumulative construction impact due to the
concurrent activities of the current projects including the Central Reclamation
Phase III, Central-Wanchai Bypass and Island Eastern Corridor Link projects.
7.0.2.
According to the Monthly EM&A report (August 2012) of Central
Reclamation Phase III (CRIII), filling works, building construction works and
pipe works were performed in the September 2012 reporting month. The water
quality monitoring was completed in October 2011 and no exceedance was recorded
for air and noise monitoring. It can be concluded that cumulative construction
impact due to the concurrent activities of the current projects with the
Central Reclamation Phase III (CRIII) was insignificant.
7.0.3.
According to the construction programme of Wan Chai
Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link
projects, the major construction activities at Reclamation Shoreline Sub-zones
under Wan Chai Development Phase II were the dredging and filling at HKCEC3w,
dredging at submarine sewage pipelines, reinstatement of seawall block
construction at TCBR1W and marine bored piling at MTR Tunnel Crossing in the
reporting month. The major environmental impact was water quality impact at,
7.0.4.
The major environmental impacts generated from the reclamation
work at Central Reclamation Phase III were only located along the coastline of
Central and Admiralty. As no project related exceedance was recorded in the
Project, it was considered no adverse environmental impact caused by the
Project works. Thus, it is evaluated the cumulative construction impact was
insignificant.
8.0.1.
During this reporting month, weekly environmental
site audits were conducted for Contracts no. HK/2009/01, HK/2009/02, HY/2009/15,
HK/2010/06 and HY/2009/19. No non-conformance was identified during the site
audits.
8.0.2.
Five site inspections for Contract no. HK/2009/01
were carried out on 29 August 2012, 5, 12, 20 and 26 September 2012 in
reporting month. Results of these inspections and outcomes are summarized in
Table 8.1.
Table 8.1 Summary
of Environmental Inspections for Contract no. HK/2009/01
Item |
Date |
Observations |
Action taken by
Contractor |
Outcome |
120829_01 |
29-Aug-12 |
The oil stain should be removed and disposed as chemical waste.
(VIP area) |
The oil stain was removed |
Completion as observed on 5-Sep-12 |
120905_01 |
5-Sep-12 |
Drip trays should be provided for oil drums (TST) |
The oil drums were removed. |
Completion as observed on 12-Sep-12 |
120912_01 |
12-Sep-12 |
The soil from the site area was observed on the public area which
should be removed immediately (A4-3) |
The exposed soil was removed |
Completion as observed on 20-Sep-12 |
120912_02 |
12-Sep-12 |
The construction materials should be moved away from the plants
(A1-1) |
The construction material was removed. |
Completion as observed on 20-Sep-12 |
120920_02 |
20-Sep-12 |
Existing trees to be retained shall be kept free from
construction materials (C1 Site office) |
The construction material was removed. |
Completion as observed on 26-Sep-12 |
120926_01 |
26-Sep-12 |
Drip tray should be provided for oil drums (Water Channel) |
The oil drums were removed. |
Completion as observed on 3-Oct-12 |
8.0.3.
Five site inspections for Contract no. HK/2009/02
were carried out on 30 August 2012, 6, 13, 19 and 27 September 2012 during this
reporting period. The results of these inspections and outcomes are summarized
in Table 8.2.
Table 8.2 Summary
of Environmental Inspections for Contract no. HK/2009/02
Item |
Date |
Observations |
Action taken by
Contractor |
Outcome |
120830_01 |
30-Aug-12 |
The valid noise emission label should be displayed on hand-held
breaker (SPCA) |
The hand-held breaker was removed from the site. |
Completion
as observed on 6-Sep-12 |
120830_02 |
30-Aug-12 |
The measures should be taken to improve the efficiency of wheel
washing facilities (Small Ex-pet garden, Gate 2 in WCR1) |
The efficiency of wheel washing facilities has been improved. |
Completion
as observed on 6-Sep-12 |
120906_01 |
6-Sep-12 |
The stockpile should be covered by tarpaulin sheet (Small Ex-pet
garden) |
The stockpile was removed, |
Completion
as observed on 13-Sep-12 |
120919_01 |
19-Sep-12 |
The lubricating oil was observed on ground which should be
cleaned and removed as chemical waste (WCR1) |
The oil was removed. |
Completion
as observed on 26-Sep-12 |
8.0.4.
Five site inspections for Contract no. HY/2009/15
were carried out on 28 August 2012, 4, 11, 18 and 25 September 2012 in reporting
month. The results of these inspections and outcomes are summarized in Table
8.3.
Table 8.3 Summary
of Environmental Inspections for Contract no. HY/2009/15
Date |
Observations |
Action taken by
Contractor |
Outcome |
|
28-Aug-12 |
120828_01 |
No stock of silt curtain, impermeable barrier
and geotextile was available on site (TS1). |
Stock of impermeable barriers and silt curtains
were stored on storage facility at North Point. |
Completion as observed on 4-Sep-12 |
28-Aug-12 |
120828_02 |
Silt curtains and impermeable barriers were
observed to be inadequate at TS1.
Better maintenance should be performed to avoid gaps & holes.
(Diaphragm wall, TS1) |
Works at TS1 were completed. |
Completion as observed on 4-Sep-12 |
28-Aug-12 |
120828_03 |
Mud was observed on the seawall blocks,
contractor should clear it to avoid runoff into sea. Protection should also be provided
(Eastern Breakwater, TS1). |
Mud was cleared from the seawall blocks. |
Completion as observed on 4-Sep-12 |
28-Aug-12 |
120828_04 |
Haul roads should be kept wet (TS4) |
Haul roads were sprayed with water. |
Completion as observed on 4-Sep-12 |
18-Sep-12 |
120918_01 |
Silty water was observed to be discharging at
discharge point. Contractor
immediately stopped discharging, but the contractor is recommended to review
the frequency of sludge removal at water treatment plants (TS4) |
Sludge was removed. |
Completion as observed on 25-Sep-12 |
25-Sep-12 |
120925_01 |
Oil leakage should be cleared up as chemical
waste. Preventive measures should
be provided for prevention of oil leakage. Drip trays should also be provided for
oil/chemical drums. |
Oil leakage was cleared. |
Completion as observed on 3-Oct-12 |
8.0.5.
Four site
inspections for Contract no. HK/2010/06 was carried out on 3, 10, 20 and 24 September 2012 in reporting month. The results of these
inspections and outcomes are summarized in Table 8.4.
Table 8.4 Summary
of Environmental Inspections for Contract no. HK/2010/06
Item |
Date |
Observations |
Action taken by
Contractor |
Outcome |
120903_01 |
3-Sep-12 |
The U-channel should be
connected with oil interceptor (2w) |
The u-channel was
connected with oil interceptor |
Completion as observed
on 10-Sep-12 |
121003_01 |
3-Oct-12 |
The oil stain was
observed on the ground which should be removed and disposed as chemical
waste.(2w) |
The oil stain was
removed as chemical waste. |
Completion as observed
on 8-Oct-12 |
8.0.6.
Five site inspections for Contract no. HY/2009/19
were carried out on 30 August 2012, 5, 12, 19 and 26 September 2012 in
reporting month. The results of these inspections and outcomes are summarized
in Table 8.5.
Table 8.5 Summary
of Environmental Inspections for Contract no. HY/2009/19
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
120830_01 |
30-Aug-12 |
The oil stain was
observed on the ground which should be removed and disposed as chemical waste
(Portion3, D7 and Portion 6, F5) |
Oil stain was removed
as chemical waste. |
Completion as observed
on 12-Sep-12 |
120912_01 |
12-Sep-12 |
Oil leakage was
observed on the water surface and on platform 9. The contractor should provide measures
to prevent further leakage. |
Oil leakage was removed
and tarpaulin sheet was provided below the leaking plant. |
Completion as observed
on 19-Sep-12 |
120926_01 |
26-Sep-12 |
Oil leakage was
observed at some plants & vehicles, the contractor is recommended to
provide adequate measures to prevent leakage and treat leakage as chemical
waste. Also, the contractor is
recommended to provide training to all staff on how to handle chemical waste
(Portion VII & Platform FVII) |
Oil leakage was
removed. |
Completion as observed
on 3-Oct-12 |
9.0.1.
There was no complaint received in this reporting month.
9.0.2.
The details of cumulative complaint log and updated
summary of complaints are presented in Appendix 9.1.
9.0.3.
Cumulative statistic on complaints and successful
prosecutions are summarized in Table 9.1 and Table 9.2
respectively.
Table 9.1 Cumulative
Statistics on Complaints
Reporting Period |
No. of Complaints |
Commencement works (Mar 2010) to last
reporting month |
27 |
September 2012 |
0 |
Project-to-Date |
27 |
Table 9.2 Cumulative
Statistics on Successful Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this month (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
10.0.1.
The EM&A programme was carried out in
accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
10.0.2.
WDII/RSS
advised that the dredging works for submarine pipeline at
10.0.3.
Oil
Street Community Liaison Centre was confirmed to be demolished in mid-October
by CWB RSS. This presented a need
for relocation of RTN2 ¡V Oil Street Community Liaison Centre. After liaison with Hong Kong Electric,
permission was granted on 21 Sep 2012 for real time noise monitoring set up at
City Garden Electric Centre (RTN2a-Electric Centre), which is a representative
of the noise sensitive
10.0.4.
Water
quality monitoring at WSD10 and WSD15 will be temporary suspended while water
quality monitoring at WSD9 and WSD17 were implemented with respect to
HK/2009/02 for the water quality monitoring scheduled on 8 Feb 12 onwards;
10.0.5.
Water
quality monitoring at C8 and C9 have been implemented with respect to HY/2009/19
since the marine bore piling work started
on 28 January 2012.
10.0.6.
Based
on the safety concern when external façade refurbishment was conducted by
contractor employed by Provident Centre (C9) between 9 January 2012 to 30 July
2012 which caused to the inaccessibility of sampling either land and marine
since 3 Feb 2012, there is a fine adjustment of the sampling location of water
quality monitoring at C9 since 10 March 2012 to the closest accessible point
prior to the completion of the external façade refurbishment work.
10.0.7.
Due
to the access of water monitoring station at WSD19 was blocked by LCSD
construction works from 3 April 2012 to 2 May 2012 and lead to the
inaccessibility of sampling either land and marine, there is a fine adjustment
of the sampling point of WSD 19 since 5 April 2012 to the closest accessible
point prior to the completion of the construction activities.
10.0.8.
With respect to the trial
dredging at WCR2 was scheduled on 20, 22, 24, 25 March and 1, 3, 11, 13, 15, 17, 19, 20 Apr and 3 May 2012, on-going water quality monitoring results at WSD21 during
this period was checked and indicated that there was no contribution due to the
trial dredging operation. Enhanced review of water quality around WCR2
was also implemented and no deterioration in the water quality was observed.
10.0.9. Due to the dredging works for Cross Harbour Water Mains from Wan
Chai to Tsim Sha Tsui- DP6 was completed on 26 March 2012, the temporary
suspension of impact water quality monitoring at WSD7 and WSD20 after 27 April
2012 for the water quality monitoring at WSD7 and WSD20 have been monitored for
4-week period after the completion of DP6 to confirm no water deterioration.
10.0.10.
The scheduled construction activities and the
recommended mitigation measures for the coming month are listed in Table
10.1.
Table 10.1 Construction Activities
and Recommended Mitigation Measures in Coming Reporting Month
Contract No. |
Key Construction Works |
Recommended Mitigation Measures |
HK/2009/01 |
Marine Works ¡P
Fabrication of 3 nos. precast concrete caisson
seawall was in progress and anticipated to be delivered to Site ¡P
Dredging works for Type 3 sediment underneath ¡P
Installation pipe pile wall for modification of
vertical seawall near ¡P
Rockfilling at east of HKCEC near ¡P
Trust block construction and rockfilling
protection works for cross-harbour watermains in ¡P
Reinstatement works at TST seashore including
removal of silt screen and demobilization of jack-up barge Fresh Watermains, Cooling Watermains and Salt Watermains (On Land) ¡P
Zone B1-5A, B2-1, B5-1(Switch Room), B5- 3(Switch
Room), A1-1, A1-2, A2-2, A3-2A, A3-4B, run-out of Renaissance Hotel and C1-10
¡P
Mainlaying works at Zone C1-10 and run-out of
Renaissance Hotel ¡P
Reinstatement works at Zone B4-3 and B4-1A ¡P
Mainlaying works at ¡P
Mainlaying works at ¡P
Workfront at Zone A1-4 (CHWM) ¡P
Mainlaying works at traffic island near junction
between ¡P
Mainlaying works at Zone A3-4B, A3-4A & A3-5A,
Zone A3-4B ¡P
Pipe laying works for cross harbour watermains
across HKCEC water channel ¡P
Final cleaning, CCTV inspection and pressure test
for the 9 nos. cooling watermains |
¡P
To conform the installation and setting as in
the silt screen deployment plan ¡P
Frequency spray water on the dry dusty road
and on the surface of concrete breaking ¡P
To cover the dusty material or stockpile by
impervious sheet ¡P
To space out noisy
equipment and position as far as possible from sensitive receiver. ¡P
To well maintain
the mechanical equipments / machineries to avoid abnormal noise nuisance. ¡P
Machines and plant
that may be in intermittent use should be shut down between work periods or
should be throttled down to a minimum ¡P
Daily visual inspection of silt screen and
silt curtain to ensure its operation properly |
HK/2009/02 |
¡P
Commence drainage diversion works to suit TWCR4
construction. ¡P
Complete diversion of uncharted drainage works at
Box culvert ¡§O¡¨. ¡P
Commence trial excavation and preparation works
for Hung Hing Road Diversion ¡P
Commence caisson seawall precast unit 2X in-situ
work on flat-top barge. ¡P
Commence seawall strengthening works at WCR2
area. ¡P
Complete PTI modification works after completion
of New Public Toilet in ¡P
Complete all cooling mains and cabling works for
P7, P8 & P9 Pumping Stations permanent power-on and signal control. ¡P
Continue 800MS pipe installation inside ¡P
Conduct Fire Service Inspection of WSD Salt Water Pumping Station on 27
Sept 2012 ¡P
Complete the finishing works of WSD Salt Water
Pumping Station. ¡P
Continue construction of Bay 1b ¡V 2, Bay 6 ¡V 8
salt water intake culverts at WCR1 area. ¡P
Complete ELS of the salt water intake ¡P
Continue salt water intake culvert at transition
bays inside jacking pit and receiving pit. ¡P
Continue remaining drainage works and reinstatement
works along ¡P
Continue HDPE piping on UU Bridge and inside
outfall seaside cofferdam. ¡P
Continue construction for Box Culvert N1 at WCR1
area. ¡P
Complete concreting works for the Level 2 at the
New Ferry Pier. |
¡P
To cover the dusty material or stockpile by
impervious sheet; ¡P
Frequency spray water on the dry dusty road
and on the surface of concrete breaking ¡P
To well maintain the mechanical equipments /
machineries to avoid abnormal noise nuisance and dark smoke emission ¡P
To conform the installation and setting as in
the silt screen and silt curtain deployment
plan ¡P
Movable noise
barrier shall be deployed for demolition works ¡P
Daily visual inspection of silt screen and
silt curtain to ensure its operation properly ¡P
Review silt screen
deployment and silt curtain deployment and resubmit associate
plans to EPD ¡P
Implement silt
screen and silt curtain in accordance with the associated plans submitted to
EPD. |
HY/2009/15 |
¡P
TZ1 reclamation works ¡P
Seawall trench works at TS2 ¡P
Formation of temporary seawall at TS2 |
¡P
Watering
any dust generating activities ¡P
Checking
all drip trays frequently and clear any stagnant water and mud inside it. ¡P
Noise
control measures shall be provided during restricted hours. |
HK/2010/06 |
¡P
Pile head breaking ¡P
Platform Disassembly ¡P
Sonic tube trimming |
¡P
To conform the installation and setting as in
the silt screen and silt curtain deployment
plan ¡P
To space out noisy
equipment and position as far as possible from sensitive receiver. ¡P
Daily visual inspection of silt screen and
silt curtain to ensure its operation properly |
HY/2009/19 |
¡P
Construction works
for Box Culvert T ¡P
Marine Piling ¡P
Construction of 1500f drainage pipe |
¡P
To conform the installation and setting as in
the silt screen and silt curtain deployment
plan |